Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
26,104
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
DL0257 # 05 Y:2025 | 05 | 2025 | INSTALL TIMERS AND/OR THERMOSTATS | $291 | $131 | n/a |
DL0257 # 01 Y:2025 | 01 | 2025 | USE SOLAR HEAT TO MAKE ELECTRICTY | $58,383 | $470,000 | n/a |
DL0257 # 03 Y:2025 | 03 | 2025 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $343 | $0 | n/a |
DL0257 # 02 Y:2025 | 02 | 2025 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $4,000 | $0 | n/a |
DL0257 # 04 Y:2025 | 04 | 2025 | USE OPTIMUM TEMPERATURE | $1,329 | $0 | n/a |
LE0599 # 06 Y:2025 | 06 | 2025 | USE CLOSED CYCLE PROCESS TO MINIMIZE WASTE WATER PRODUCTION | $98,974 | $65,000 | n/a |
LE0599 # 03 Y:2025 | 03 | 2025 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $24,855 | $7,000 | n/a |
LE0599 # 09 Y:2025 | 09 | 2025 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $8,397 | $22,164 | n/a |
LE0599 # 02 Y:2025 | 02 | 2025 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $3,295 | $100 | n/a |
LE0599 # 01 Y:2025 | 01 | 2025 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $15,231 | $50 | n/a |
LE0599 # 10 Y:2025 | 10 | 2025 | USE SOLAR HEAT TO MAKE ELECTRICTY | $39,348 | $166,600 | n/a |
LE0599 # 04 Y:2025 | 04 | 2025 | UPGRADE OBSOLETE EQUIPMENT | $66,584 | $25,000 | n/a |
LE0599 # 05 Y:2025 | 05 | 2025 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,274 | $2,000 | n/a |
LE0599 # 11 Y:2025 | 11 | 2025 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $32,291 | $137,607 | n/a |
LE0599 # 07 Y:2025 | 07 | 2025 | BURN A LESS EXPENSIVE GRADE OF FUEL | $2,581 | $4,000 | n/a |
LE0599 # 08 Y:2025 | 08 | 2025 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $808 | $1,500 | n/a |
LE0599 # 12 Y:2025 | 12 | 2025 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,690 | $12,500 | n/a |
OK1137 # 08 Y:2025 | 08 | 2025 | CONSERVE ENERGY BY EFFICIENT USE OF VENDING MACHINES | $558 | $410 | n/a |
OK1137 # 03 Y:2025 | 03 | 2025 | USE SOLAR HEAT TO MAKE ELECTRICTY | $31,249 | $160,056 | n/a |
OK1137 # 04 Y:2025 | 04 | 2025 | OPTIMIZE PLANT POWER FACTOR | $3,482 | $12,000 | n/a |
OK1137 # 05 Y:2025 | 05 | 2025 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,886 | $1,320 | n/a |
OK1137 # 02 Y:2025 | 02 | 2025 | INSTALL OCCUPANCY SENSORS | $520 | $1,286 | n/a |
OK1137 # 01 Y:2025 | 01 | 2025 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $641 | $985 | n/a |
OK1137 # 06 Y:2025 | 06 | 2025 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $8,920 | $6,940 | n/a |
OK1137 # 07 Y:2025 | 07 | 2025 | COMBINE UTILITY METERS | $682 | $80 | n/a |