IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

2,756

matching recommendations
Reset
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
OR0710 # 02 Y:2018 02 2018 USE CLOSED CYCLE PROCESS TO MINIMIZE WASTE WATER PRODUCTION $31,220 $60,550 Not Implemented
OR0710 # 03 Y:2018 03 2018 UPGRADE CONTROLS ON COMPRESSORS $15,485 $1,280 Not Implemented
OR0710 # 04 Y:2018 04 2018 REPLACE PURCHASED STEAM WITH OTHER ENERGY SOURCE $19,538 $19,269 Not Implemented
OR0710 # 05 Y:2018 05 2018 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $12,922 $12,567 Not Implemented
OR0710 # 06 Y:2018 06 2018 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $4,410 $3,742 Not Implemented
OR0710 # 07 Y:2018 07 2018 MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE $12,550 $1,000 Not Implemented
UF0521 # 01 Y:2018 01 2018 INCREASE AMOUNT OF CONDENSATE RETURNED $45,855 $11,386 Implemented
UF0521 # 02 Y:2018 02 2018 USE SOLAR HEAT TO MAKE ELECTRICTY $41,132 $314,072 Implemented
UF0521 # 03 Y:2018 03 2018 REPAIR AND ELIMINATE STEAM LEAKS $13,844 $562 Implemented
UF0521 # 04 Y:2018 04 2018 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $10,195 $15,000 Implemented
UF0521 # 05 Y:2018 05 2018 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $7,972 $4,143 Implemented
UF0521 # 06 Y:2018 06 2018 IMPROVE COMBUSTION CONTROL CAPABILITY $3,586 $2,800 Implemented
UF0521 # 07 Y:2018 07 2018 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $1,356 $0 Implemented
UF0521 # 08 Y:2018 08 2018 INSTALL OCCUPANCY SENSORS $1,160 $1,149 Implemented
UF0521 # 09 Y:2018 09 2018 RE-ARRANGE EQUIPMENT LAYOUT TO REDUCE HANDLING COSTS $39,645 $66,000 Implemented
UF0521 # 10 Y:2018 10 2018 MAKE A NEW BY-PRODUCT $243,164 $58,810 Implemented
UK1811 # 01 Y:2018 01 2018 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $3,721 $2,250 Not Implemented
UK1811 # 02 Y:2018 02 2018 ELIMINATE/REDUCE AN OPERATION $2,899 $0 Not Implemented
UK1811 # 03 Y:2018 03 2018 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $6,133 $2,270 Implemented
UK1811 # 04 Y:2018 04 2018 REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS $372 $0 Not Implemented
UK1811 # 05 Y:2018 05 2018 VENTILATION SYSTEM TO SHUT OFF WHEN ROOM IS NOT IN USE $2,503 $0 Implemented
UK1811 # 06 Y:2018 06 2018 PREHEAT COMBUSTION AIR WITH WASTE HEAT $5,397 $3,780 Not Implemented
UK1811 # 07 Y:2018 07 2018 INSTALL OCCUPANCY SENSORS $2,332 $4,270 Implemented
UK1811 # 08 Y:2018 08 2018 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $282 $164 Implemented
TT0211 # 01 Y:2018 01 2018 FLASH CONDENSATE TO PRODUCE LOWER PRESSURE STEAM $115,103 $150,000 Implemented