IAC Assessment: AR0080
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: AR0080
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Arkansas
Assessment Year 1996
Principal Product 12,000 Btu Fuel
NAICS n/a
SIC 2869 - Industrial Organic Chemicals, Nec
Sales $10,000,000-$50,000,000
# of Employees 225
Plant Area (Sq.Ft.) 54,000
Annual Production 9,900,000 Thousand Gallons
Production Hrs. Annual 8,760
Location (State) AR
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $43,095 2,076,788 kWh $0.02
Electricity Demand $79,832 4,469 kW-months/year $17.86
Natural Gas $730 129 MMBtu $5.66
TOTAL ENERGY COSTS $165,161
RECOMMENDED SAVINGS* $78,911 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $78,911
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Solid Waste (non-haz) Electricity Usage Electricity Demand Solid Waste (non-haz)
$ kWh $ kW-months/year $ lb
01: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS Savings:
$4,133
Cost:
$7,570
$1,418 67,409 $2,715 151 - - $1,418
67,409
kWh
$2,715
151
kW-months/year
-
-
lb
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$1,604
Cost:
$364
$738 35,170 $866 48 - - $738
35,170
kWh
$866
48
kW-months/year
-
-
lb
03: 2.7111 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS Savings:
$6,114
Cost:
$80
$1,279 61,254 $4,835 269 - - $1,279
61,254
kWh
$4,835
269
kW-months/year
-
-
lb
04: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS Savings:
$337
Cost:
$100
$290 13,775 $47 3 - - $290
13,775
kWh
$47
3
kW-months/year
-
-
lb
05: 2.1114 LIMIT AND CONTROL SECONDARY COMBUSTION AIR IN FURNACE Savings:
$41,971
Cost:
$11,500
$19,316 919,402 $22,655 1,260 - - $19,316
919,402
kWh
$22,655
1,260
kW-months/year
-
-
lb
06: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS Savings:
$608
Cost:
-
$153 7,327 $455 25 - - $153
7,327
kWh
$455
25
kW-months/year
-
-
lb
07: 3.5315 LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER Savings:
$24,144
Cost:
$1,000
- - - - $24,144 448,000 -
-
kWh
-
-
kW-months/year
$24,144
448,000
lb
TOTAL RECOMMENDED Savings:
$78,911
Cost:
$20,614
$23,194 1,104,337 $31,573 1,756 $24,144 448,000 $23,194
1,104,337
kWh
$31,573
1,756
kW-months/year
$24,144
448,000
lb
TOTAL IMPLEMENTED Savings:
$78,911
Cost:
$20,614
$23,194 1,104,337 $31,573 1,756 $24,144 448,000 $23,194
1,104,337
kWh
$31,573
1,756
kW-months/year
$24,144
448,000
lb
Savings
Cost
$ kWh $ kW-months/year $ lb
Electricity Usage Electricity Demand Solid Waste (non-haz) Electricity Usage Electricity Demand Solid Waste (non-haz)