IAC Assessment: AR0125
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: AR0125
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Arkansas
Assessment Year 1997
Principal Product Fractional Horsepower A/C and D/C Motors
NAICS n/a
SIC 3621 - Motors And Generators
Sales $10,000,000-$50,000,000
# of Employees 325
Plant Area (Sq.Ft.) 90,000
Annual Production 6,000,000 Pieces
Production Hrs. Annual 5,640
Location (State) AR
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $94,470 3,315,651 kWh $0.03
Electricity Demand $139,944 9,069 kW-months/year $15.43
Natural Gas $27,307 5,294 MMBtu $5.16
TOTAL ENERGY COSTS $265,413
RECOMMENDED SAVINGS* $56,024 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $44,717
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Water Disposal Personnel Changes Electricity Usage Electricity Demand Water Disposal Personnel Changes
$ kWh $ kW-months/year $ Tgal $ $
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$6,053
Cost:
$1,212
$2,629 93,787 $3,424 19 - - - - $2,629
93,787
kWh
$3,424
19
kW-months/year
-
-
Tgal
-
-
$
02: 2.7111 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS Savings:
$1,085
Cost:
$186
$449 16,120 $636 3 - - - - $449
16,120
kWh
$636
3
kW-months/year
-
-
Tgal
-
-
$
03: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS Savings:
$200
Cost:
$229
$88 3,517 $112 1 - - - - $88
3,517
kWh
$112
1
kW-months/year
-
-
Tgal
-
-
$
04: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS Savings:
$265
Cost:
-
$122 4,396 $143 1 - - - - $122
4,396
kWh
$143
1
kW-months/year
-
-
Tgal
-
-
$
05: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$1,152
Cost:
$150
$530 19,050 $622 3 - - - - $530
19,050
kWh
$622
3
kW-months/year
-
-
Tgal
-
-
$
06: 2.3136 OVERLAP CUSTODIAL SERVICES WITH NORMAL DAY HOURS Savings:
$89
Cost:
-
$89 3,224 - 9 - - - - $89
3,224
kWh
-
9
kW-months/year
-
-
Tgal
-
-
$
07: 3.4115 RECOVER AND REUSE COOLING WATER Savings:
$6,309
Cost:
$8,400
$(-459) (-8,499) - - $6,768 4,230,000 - - $(-459)
(-8,499)
kWh
-
-
kW-months/year
$6,768
4,230,000
Tgal
-
-
$
08: 3.4115 RECOVER AND REUSE COOLING WATER Savings:
$4,837
Cost:
$31,000
$(-918) (-16,999) - - $5,755 3,597,000 - - $(-918)
(-16,999)
kWh
-
-
kW-months/year
$5,755
3,597,000
Tgal
-
-
$
09: 4.5130 RE-ARRANGE EQUIPMENT LAYOUT TO REDUCE LABOR COSTS Savings:
$31,334
Cost:
$2,000
- - - - - - $31,334 - -
-
kWh
-
-
kW-months/year
-
-
Tgal
$31,334
-
$
10: 4.5130 RE-ARRANGE EQUIPMENT LAYOUT TO REDUCE LABOR COSTS Savings:
$4,700
Cost:
$1,000
- - - - - - $4,700 - -
-
kWh
-
-
kW-months/year
-
-
Tgal
$4,700
-
$
TOTAL RECOMMENDED Savings:
$56,024
Cost:
$44,177
$2,530 114,596 $4,937 36 $12,523 7,827,000 $36,034 - $2,530
114,596
kWh
$4,937
36
kW-months/year
$12,523
7,827,000
Tgal
$36,034
-
$
TOTAL IMPLEMENTED Savings:
$44,717
Cost:
$41,736
$(-398) 9,672 $1,258 6 $12,523 7,827,000 $31,334 - $(-398)
9,672
kWh
$1,258
6
kW-months/year
$12,523
7,827,000
Tgal
$31,334
-
$
Savings
Cost
$ kWh $ kW-months/year $ Tgal $ $
Electricity Usage Electricity Demand Water Disposal Personnel Changes Electricity Usage Electricity Demand Water Disposal Personnel Changes