Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Arizona State University |
---|---|
Assessment Year | 1997 |
Principal Product | Anodizing |
NAICS | n/a |
SIC | 3471 - Plating And Polishing |
Sales | $5,000,000-$10,000,000 |
# of Employees | 150 |
Plant Area (Sq.Ft.) | 60,000 |
Annual Production | 1,036,000 Pieces |
Production Hrs. Annual | 8,760 |
Location (State) | AZ |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $332,834 | 4,523,447 | kWh | $0.07 |
Electricity Demand | $19,600 | 11,135 | kW-months/year | $1.76 |
Electricity Fees | $24,146 | - | $ | - |
Natural Gas | $9,574 | 1,715 | MMBtu | $5.58 |
TOTAL ENERGY COSTS | $402,029 | |||
RECOMMENDED SAVINGS* | $53,613 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $17,017 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Water Disposal | Solid Waste (non-haz) | Personnel Changes | Administrative Changes | Electricity Usage | Electricity Demand | Water Disposal | Solid Waste (non-haz) | Personnel Changes | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | Tgal | $ | lb | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7228 AVOID INTRODUCING HOT, HUMID, OR DIRTY AIR INTO HVAC SYSTEM |
Savings: $11,182 Cost: $2,080 |
$7,607 | 154,748 | $3,575 | 423 | - | - | - | - | - | - | - | - |
$7,607 154,748 kWh |
$3,575 423 kW-months/year |
- - Tgal |
- - lb |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $5,290 Cost: $7,006 |
$4,375 | 88,804 | $915 | 108 | - | - | - | - | - | - | - | - |
$4,375 88,804 kWh |
$915 108 kW-months/year |
- - Tgal |
- - lb |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $815 Cost: $70 |
$623 | 12,603 | $192 | 23 | - | - | - | - | - | - | - | - |
$623 12,603 kWh |
$192 23 kW-months/year |
- - Tgal |
- - lb |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $2,230 Cost: $1,092 |
$1,806 | 36,635 | $424 | 50 | - | - | - | - | - | - | - | - |
$1,806 36,635 kWh |
$424 50 kW-months/year |
- - Tgal |
- - lb |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7232 REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL |
Savings: $8,943 Cost: $7,500 |
$7,218 | 146,835 | $1,725 | 204 | - | - | - | - | - | - | - | - |
$7,218 146,835 kWh |
$1,725 204 kW-months/year |
- - Tgal |
- - lb |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $714 Cost: $40 |
$578 | 11,723 | $136 | 16 | - | - | - | - | - | - | - | - |
$578 11,723 kWh |
$136 16 kW-months/year |
- - Tgal |
- - lb |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7111 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS |
Savings: $1,901 Cost: $70 |
$1,279 | 26,084 | $622 | 74 | - | - | - | - | - | - | - | - |
$1,279 26,084 kWh |
$622 74 kW-months/year |
- - Tgal |
- - lb |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $1,348 Cost: $1,425 |
$1,208 | 24,619 | $140 | 17 | - | - | - | - | - | - | - | - |
$1,208 24,619 kWh |
$140 17 kW-months/year |
- - Tgal |
- - lb |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 3.4113 TREAT AND REUSE RINSE WATERS |
Savings: $4,004 Cost: $950 |
- | - | - | - | $4,004 | 1,300,000 | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$4,004 1,300,000 Tgal |
- - lb |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 3.1191 CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS |
Savings: $15,110 Cost: $4,500 |
- | - | - | - | - | - | $5,360 | 1,000 | $9,750 | - | - | - |
- - kWh |
- - kW-months/year |
- - Tgal |
$5,360 1,000 lb |
$9,750 - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
11: 3.6192 USE A LESS EXPENSIVE METHOD OF WASTE REMOVAL |
Savings: $2,076 Cost: $30 |
- | - | - | - | - | - | - | - | - | - | $2,076 | - |
- - kWh |
- - kW-months/year |
- - Tgal |
- - lb |
- - $ |
$2,076 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $53,613 Cost: $24,763 |
$24,694 | 502,051 | $7,729 | 915 | $4,004 | 1,300,000 | $5,360 | 1,000 | $9,750 | - | $2,076 | - | $24,694 502,051 kWh |
$7,729 915 kW-months/year |
$4,004 1,300,000 Tgal |
$5,360 1,000 lb |
$9,750 - $ |
$2,076 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $17,017 Cost: $3,312 |
$10,614 | 215,709 | $4,327 | 512 | - | - | - | - | - | - | $2,076 | - | $10,614 215,709 kWh |
$4,327 512 kW-months/year |
- - Tgal |
- - lb |
- - $ |
$2,076 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | Tgal | $ | lb | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Water Disposal | Solid Waste (non-haz) | Personnel Changes | Administrative Changes | Electricity Usage | Electricity Demand | Water Disposal | Solid Waste (non-haz) | Personnel Changes | Administrative Changes |