IAC Assessment: AS0272
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: AS0272
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Arizona State University
Assessment Year 2000
Principal Product Plastic Injection Molding
NAICS n/a
SIC 3089 - Plastics Products, Nec
Sales $5,000,000-$10,000,000
# of Employees 40
Plant Area (Sq.Ft.) 42,000
Annual Production 13,500 Pounds
Production Hrs. Annual 5,046
Location (State) AZ
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $62,654 689,918 kWh $0.09
Electricity Demand $4,958 3,149 kW-months/year $1.57
Electricity Fees $72,330 - $ -
LPG $3,777 334 MMBtu $11.31
TOTAL ENERGY COSTS $144,518
RECOMMENDED SAVINGS* $19,542 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $18,772
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Administrative Changes Ancillary Material Cost Electricity Usage Electricity Demand Administrative Changes Ancillary Material Cost
$ kWh $ kW-months/year $ $ $ $
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$160
Cost:
$145
$92 1,172 $19 2 $24 - $25 - $92
1,172
kWh
$19
2
kW-months/year
$24
-
$
$25
-
$
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$15,392
Cost:
$14,863
$13,076 175,264 $2,316 439 - - - - $13,076
175,264
kWh
$2,316
439
kW-months/year
-
-
$
-
-
$
03: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS Savings:
$502
Cost:
$781
$430 5,862 $72 14 - - - - $430
5,862
kWh
$72
14
kW-months/year
-
-
$
-
-
$
04: 2.7135 INSTALL OCCUPANCY SENSORS Savings:
$405
Cost:
$525
$320 4,396 $85 16 - - - - $320
4,396
kWh
$85
16
kW-months/year
-
-
$
-
-
$
05: 2.7133 USE SEPARATE SWITCHES ON PERIMETER LIGHTING WHICH MAY BE TURNED OFF WHEN NATURAL LIGHT IS AVAILABLE Savings:
$365
Cost:
$150
$365 4,982 - - - - - - $365
4,982
kWh
-
-
kW-months/year
-
-
$
-
-
$
06: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS Savings:
$299
Cost:
$440
$255 2,931 $44 8 - - - - $255
2,931
kWh
$44
8
kW-months/year
-
-
$
-
-
$
07: 2.1332 CONVERT COMBUSTION EQUIPMENT TO BURN NATURAL GAS Savings:
$2,419
Cost:
$295
- - - - $2,419 - - - -
-
kWh
-
-
kW-months/year
$2,419
-
$
-
-
$
TOTAL RECOMMENDED Savings:
$19,542
Cost:
$17,199
$14,538 194,607 $2,536 479 $2,443 - $25 - $14,538
194,607
kWh
$2,536
479
kW-months/year
$2,443
-
$
$25
-
$
TOTAL IMPLEMENTED Savings:
$18,772
Cost:
$16,524
$13,853 185,229 $2,451 463 $2,443 - $25 - $13,853
185,229
kWh
$2,451
463
kW-months/year
$2,443
-
$
$25
-
$
Savings
Cost
$ kWh $ kW-months/year $ $ $ $
Electricity Usage Electricity Demand Administrative Changes Ancillary Material Cost Electricity Usage Electricity Demand Administrative Changes Ancillary Material Cost