IAC logo
IAC Assessment: AS0434
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: AS0434
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Arizona State University
Assessment Year 2017
Principal Product Precision metal parts, milled and ground to customer specifications
NAICS 334418 - Printed Circuit Assembly (Electronic Assembly) Manufacturing
SIC 3559 - Special Industry Machinery, Nec
Sales $50,000,000-$100,000,000
# of Employees 150
Plant Area (Sq.Ft.) 45,000
Annual Production 100,000 Units
Production Hrs. Annual 8,760
Location (State) AZ
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $245,067 4,114,169 kWh $0.06
Electricity Demand $52,783 23,443 kW-months/year $2.25
Electricity Fees $108,273 - $ -
TOTAL ENERGY COSTS $406,124
RECOMMENDED SAVINGS* $133,523 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $307
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Electricity Usage Electricity Demand
$ kWh $ kW-months/year
01: 2.4224 UPGRADE CONTROLS ON COMPRESSORS Savings:
$68,034
Cost:
$6,582
$66,620 693,950 $1,414 950 $66,620
693,950
kWh
$1,414
950
kW-months/year
02: 2.4224 UPGRADE CONTROLS ON COMPRESSORS Savings:
$43,502
Cost:
$4,394
$41,480 370,360 $2,022 507 $41,480
370,360
kWh
$2,022
507
kW-months/year
03: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$11,405
Cost:
$1,200
$11,108 115,710 $297 160 $11,108
115,710
kWh
$297
160
kW-months/year
04: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$7,250
Cost:
$2,513
$7,072 73,668 $178 96 $7,072
73,668
kWh
$178
96
kW-months/year
05: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED Savings:
$2,564
Cost:
$60
$2,415 21,563 $149 30 $2,415
21,563
kWh
$149
30
kW-months/year
06: 2.6242 MINIMIZE OPERATION OF EQUIPMENT MAINTAINED IN STANDBY CONDITION Savings:
$461
Cost:
$450
$461 4,803 - - $461
4,803
kWh
-
-
kW-months/year
07: 2.6212 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME Savings:
$307
Cost:
$60
$307 3,197 - - $307
3,197
kWh
-
-
kW-months/year
TOTAL RECOMMENDED Savings:
$133,523
Cost:
$15,259
$129,463 1,283,251 $4,060 1,742 $129,463
1,283,251
kWh
$4,060
1,742
kW-months/year
TOTAL IMPLEMENTED Savings:
$307
Cost:
$60
$307 3,197 - - $307
3,197
kWh
-
-
kW-months/year
Savings
Cost
$ kWh $ kW-months/year
Electricity Usage Electricity Demand Electricity Usage Electricity Demand