Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Bradley University |
---|---|
Assessment Year | 1996 |
Principal Product | Corrugated Roofing and Siding Panels |
NAICS | n/a |
SIC | 3444 - Sheet Metalwork |
Sales | n/a |
# of Employees | 34 |
Plant Area (Sq.Ft.) | 93,200 |
Annual Production | 45,000,000 Pounds |
Production Hrs. Annual | 2,080 |
Location (State) | IL |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $54,754 | 1,105,510 | kWh | $0.05 |
Electricity Demand | $37,503 | 4,448 | kW-months/year | $8.43 |
Electricity Fees | $9,428 | - | $ | - |
TOTAL ENERGY COSTS | $102,585 | |||
RECOMMENDED SAVINGS* | $22,863 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $6,772 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | LPG | By-product Production | Electricity Usage | Electricity Demand | LPG | By-product Production | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.1311 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT |
Savings: $15,772 Cost: $17,505 |
$20,150 | 429,660 | $9,352 | 1,336 | $(-13,730) | (-1,725) | - | - |
$20,150 429,660 kWh |
$9,352 1,336 kW-months/year |
$(-13,730) (-1,725) MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $2,463 Cost: $5,801 |
$1,241 | 26,377 | $1,222 | 145 | - | - | - | - |
$1,241 26,377 kWh |
$1,222 145 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $1,346 Cost: $4,140 |
$668 | 14,361 | $678 | 81 | - | - | - | - |
$668 14,361 kWh |
$678 81 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $450 Cost: $375 |
$231 | 4,982 | $219 | 26 | - | - | - | - |
$231 4,982 kWh |
$219 26 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $353 Cost: $300 |
$228 | 4,982 | $125 | 15 | - | - | - | - |
$228 4,982 kWh |
$125 15 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $319 Cost: $504 |
$256 | 5,569 | $63 | 8 | - | - | - | - |
$256 5,569 kWh |
$63 8 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 3.5316 CONTRACT A WOOD PALLET RECYCLING COMPANY |
Savings: $2,160 Cost: $370 |
- | - | - | - | - | - | $2,160 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$2,160 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $22,863 Cost: $28,995 |
$22,774 | 485,931 | $11,659 | 1,611 | $(-13,730) | (-1,725) | $2,160 | - | $22,774 485,931 kWh |
$11,659 1,611 kW-months/year |
$(-13,730) (-1,725) MMBtu |
$2,160 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $6,772 Cost: $10,986 |
$2,368 | 50,702 | $2,244 | 267 | - | - | $2,160 | - | $2,368 50,702 kWh |
$2,244 267 kW-months/year |
- - MMBtu |
$2,160 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | LPG | By-product Production | Electricity Usage | Electricity Demand | LPG | By-product Production |