Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Bradley University |
---|---|
Assessment Year | 1997 |
Principal Product | Injection Moldings |
NAICS | n/a |
SIC | 3089 - Plastics Products, Nec |
Sales | $10,000,000-$50,000,000 |
# of Employees | 140 |
Plant Area (Sq.Ft.) | 41,000 |
Annual Production | 450,000 Pounds |
Production Hrs. Annual | 6,240 |
Location (State) | IL |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $129,641 | 2,779,895 | kWh | $0.05 |
Electricity Demand | $81,024 | 6,250 | kW-months/year | $12.96 |
Electricity Fees | $1,803 | - | $ | - |
Natural Gas | $6,043 | 1,376 | MMBtu | $4.39 |
TOTAL ENERGY COSTS | $236,511 | |||
RECOMMENDED SAVINGS* | $102,927 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $62,095 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (non-haz) | Personnel Changes | Administrative Changes | Primary Raw Material | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (non-haz) | Personnel Changes | Administrative Changes | Primary Raw Material | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | lb | $ | $ | $ | $ | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.1311 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT |
Savings: $38,324 Cost: $24,791 |
$31,281 | 671,161 | $18,589 | 1,434 | $(-11,546) | (-2,946) | - | - | - | - | - | - | - | - | - | - |
$31,281 671,161 kWh |
$18,589 1,434 kW-months/year |
$(-11,546) (-2,946) MMBtu |
- - lb |
- - $ |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.8114 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE |
Savings: $37,336 Cost: $500 |
- | - | - | - | - | - | - | - | - | - | $37,336 | - | - | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - lb |
- - $ |
$37,336 - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $7,396 Cost: $8,110 |
$4,618 | 99,062 | $2,778 | 214 | - | - | - | - | - | - | - | - | - | - | - | - |
$4,618 99,062 kWh |
$2,778 214 kW-months/year |
- - MMBtu |
- - lb |
- - $ |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.1311 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT |
Savings: $3,496 Cost: $1,920 |
$3,553 | 76,202 | $1,218 | 94 | $(-1,275) | (-325) | - | - | - | - | - | - | - | - | - | - |
$3,553 76,202 kWh |
$1,218 94 kW-months/year |
$(-1,275) (-325) MMBtu |
- - lb |
- - $ |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $1,875 Cost: $2,077 |
$1,218 | 26,084 | $657 | 51 | - | - | - | - | - | - | - | - | - | - | - | - |
$1,218 26,084 kWh |
$657 51 kW-months/year |
- - MMBtu |
- - lb |
- - $ |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $1,261 Cost: $400 |
$966 | 20,809 | $295 | 23 | - | - | - | - | - | - | - | - | - | - | - | - |
$966 20,809 kWh |
$295 23 kW-months/year |
- - MMBtu |
- - lb |
- - $ |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $783 Cost: $600 |
$499 | 10,844 | $284 | 22 | - | - | - | - | - | - | - | - | - | - | - | - |
$499 10,844 kWh |
$284 22 kW-months/year |
- - MMBtu |
- - lb |
- - $ |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 3.5315 LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER |
Savings: $9,643 Cost: $7,500 |
- | - | - | - | - | - | $3,473 | 136,656 | $(-660) | - | - | - | - | - | $6,830 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$3,473 136,656 lb |
$(-660) - $ |
- - $ |
- - $ |
$6,830 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 3.5311 RECOVER AND REUSE WASTE MATERIAL |
Savings: $2,813 Cost: $2,250 |
$(-750) | (-16,120) | - | - | - | - | $132 | 21,675 | $(-3,900) | - | - | - | $7,331 | - | - | - |
$(-750) (-16,120) kWh |
- - kW-months/year |
- - MMBtu |
$132 21,675 lb |
$(-3,900) - $ |
- - $ |
$7,331 - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $102,927 Cost: $48,148 |
$41,385 | 888,042 | $23,821 | 1,838 | $(-12,821) | (-3,271) | $3,605 | 158,331 | $(-4,560) | - | $37,336 | - | $7,331 | - | $6,830 | - | $41,385 888,042 kWh |
$23,821 1,838 kW-months/year |
$(-12,821) (-3,271) MMBtu |
$3,605 158,331 lb |
$(-4,560) - $ |
$37,336 - $ |
$7,331 - $ |
$6,830 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $62,095 Cost: $45,728 |
$37,832 | 811,840 | $22,603 | 1,744 | $(-11,546) | (-2,946) | $3,605 | 158,331 | $(-4,560) | - | - | - | $7,331 | - | $6,830 | - | $37,832 811,840 kWh |
$22,603 1,744 kW-months/year |
$(-11,546) (-2,946) MMBtu |
$3,605 158,331 lb |
$(-4,560) - $ |
- - $ |
$7,331 - $ |
$6,830 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | lb | $ | $ | $ | $ | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (non-haz) | Personnel Changes | Administrative Changes | Primary Raw Material | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (non-haz) | Personnel Changes | Administrative Changes | Primary Raw Material | Ancillary Material Cost |