Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Bradley University |
---|---|
Assessment Year | 1999 |
Principal Product | Metal Fasteners |
NAICS | n/a |
SIC | 3452 - Bolts, Nuts, Rivets, And Washers |
Sales | $50,000,000-$100,000,000 |
# of Employees | 300 |
Plant Area (Sq.Ft.) | 143,000 |
Annual Production | 13,700,000 Pounds |
Production Hrs. Annual | 6,032 |
Location (State) | IL |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $521,027 | 7,371,923 | kWh | $0.07 |
Electricity Demand | $226,327 | 16,022 | kW-months/year | $14.13 |
Electricity Fees | $1,934 | - | $ | - |
Natural Gas | $35,348 | 11,526 | MMBtu | $3.07 |
TOTAL ENERGY COSTS | $821,794 | |||
RECOMMENDED SAVINGS* | $103,504 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $31,033 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Solid Waste (non-haz) | By-product Production | Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Solid Waste (non-haz) | By-product Production | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | Tgal | $ | lb | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $15,947 Cost: $28,000 |
$10,395 | 261,723 | $5,552 | 393 | - | - | - | - | - | - | - | - |
$10,395 261,723 kWh |
$5,552 393 kW-months/year |
- - MMBtu |
- - Tgal |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4314 USE SYNTHETIC LUBRICANT |
Savings: $7,711 Cost: $2,400 |
$4,515 | 113,716 | $3,196 | 226 | - | - | - | - | - | - | - | - |
$4,515 113,716 kWh |
$3,196 226 kW-months/year |
- - MMBtu |
- - Tgal |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $5,947 Cost: $4,800 |
$3,877 | 97,597 | $2,070 | 147 | - | - | - | - | - | - | - | - |
$3,877 97,597 kWh |
$2,070 147 kW-months/year |
- - MMBtu |
- - Tgal |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $3,316 Cost: - |
$1,941 | 48,945 | $1,375 | 97 | - | - | - | - | - | - | - | - |
$1,941 48,945 kWh |
$1,375 97 kW-months/year |
- - MMBtu |
- - Tgal |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.1311 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT |
Savings: $2,135 Cost: $1,200 |
$2,013 | 50,996 | $793 | 60 | $(-671) | (-218) | - | - | - | - | - | - |
$2,013 50,996 kWh |
$793 60 kW-months/year |
$(-671) (-218) MMBtu |
- - Tgal |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $1,586 Cost: $750 |
$882 | 22,274 | $704 | 50 | - | - | - | - | - | - | - | - |
$882 22,274 kWh |
$704 50 kW-months/year |
- - MMBtu |
- - Tgal |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $630 Cost: $545 |
$286 | 7,327 | $344 | 24 | - | - | - | - | - | - | - | - |
$286 7,327 kWh |
$344 24 kW-months/year |
- - MMBtu |
- - Tgal |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $275 Cost: $410 |
$185 | 4,689 | $90 | 6 | - | - | - | - | - | - | - | - |
$185 4,689 kWh |
$90 6 kW-months/year |
- - MMBtu |
- - Tgal |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 3.5112 REPROCESS SPENT OILS ON SITE FOR RE-USE |
Savings: $7,003 Cost: $5,500 |
- | - | - | - | - | - | - | - | $7,003 | 19,305 | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - Tgal |
$7,003 19,305 lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 3.4111 USE CLOSED CYCLE PROCESS TO MINIMIZE WASTE WATER PRODUCTION |
Savings: $3,154 Cost: $9,500 |
$(-397) | (-9,965) | $(-346) | (-25) | - | - | $3,897 | 682,500 | - | - | - | - |
$(-397) (-9,965) kWh |
$(-346) (-25) kW-months/year |
- - MMBtu |
$3,897 682,500 Tgal |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
11: 4.122 DEVELOP STANDARD PROCEDURES TO IMPROVE INTERNAL YIELDS |
Savings: $55,272 Cost: $5,000 |
- | - | - | - | - | - | - | - | $55,272 | 40,944 | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - Tgal |
$55,272 40,944 lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
12: 4.131 MODIFY PROCESS TO REDUCE MATERIAL USE/COST |
Savings: $528 Cost: $250 |
- | - | - | - | - | - | - | - | - | - | $528 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - Tgal |
- - lb |
$528 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $103,504 Cost: $58,355 |
$23,697 | 597,302 | $13,778 | 978 | $(-671) | (-218) | $3,897 | 682,500 | $62,275 | 60,249 | $528 | - | $23,697 597,302 kWh |
$13,778 978 kW-months/year |
$(-671) (-218) MMBtu |
$3,897 682,500 Tgal |
$62,275 60,249 lb |
$528 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $31,033 Cost: $40,855 |
$16,925 | 426,435 | $10,211 | 721 | - | - | $3,897 | 682,500 | - | - | - | - | $16,925 426,435 kWh |
$10,211 721 kW-months/year |
- - MMBtu |
$3,897 682,500 Tgal |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | Tgal | $ | lb | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Solid Waste (non-haz) | By-product Production | Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Solid Waste (non-haz) | By-product Production |