Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Bradley University |
---|---|
Assessment Year | 2001 |
Principal Product | Button Parts and Button Making Equipment |
NAICS | n/a |
SIC | 3965 - Fasteners, Buttons, Needles, & Pins |
Sales | $10,000,000-$50,000,000 |
# of Employees | 87 |
Plant Area (Sq.Ft.) | 75,000 |
Annual Production | 22,000,000 Pieces |
Production Hrs. Annual | 6,240 |
Location (State) | IL |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $36,888 | 804,900 | kWh | $0.05 |
Electricity Demand | $18,213 | 2,478 | kW-months/year | $7.35 |
Electricity Fees | $2,538 | - | $ | - |
Natural Gas | $4,932 | 1,004 | MMBtu | $4.91 |
TOTAL ENERGY COSTS | $63,816 | |||
RECOMMENDED SAVINGS* | $117,789 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $6,760 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Water Disposal | Administrative Changes | One-time Revenue or Avoided Cost | Electricity Usage | Electricity Demand | Water Disposal | Administrative Changes | One-time Revenue or Avoided Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | Tgal | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4239 ELIMINATE OR REDUCE COMPRESSED AIR USAGE |
Savings: $1,232 Cost: $4,400 |
$1,184 | 25,849 | $48 | 7 | - | - | - | - | - | - |
$1,184 25,849 kWh |
$48 7 kW-months/year |
- - Tgal |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $776 Cost: $667 |
$366 | 7,989 | $80 | 11 | - | - | - | - | $330 | - |
$366 7,989 kWh |
$80 11 kW-months/year |
- - Tgal |
- - $ |
$330 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $752 Cost: $300 |
$575 | 12,564 | $177 | 24 | - | - | - | - | - | - |
$575 12,564 kWh |
$177 24 kW-months/year |
- - Tgal |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $417 Cost: $525 |
$230 | 5,014 | $187 | 25 | - | - | - | - | - | - |
$230 5,014 kWh |
$187 25 kW-months/year |
- - Tgal |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $334 Cost: $200 |
$255 | 5,575 | $79 | 11 | - | - | - | - | - | - |
$255 5,575 kWh |
$79 11 kW-months/year |
- - Tgal |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4314 USE SYNTHETIC LUBRICANT |
Savings: $328 Cost: $500 |
$251 | 5,474 | $77 | 11 | - | - | - | - | - | - |
$251 5,474 kWh |
$77 11 kW-months/year |
- - Tgal |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $178 Cost: $710 |
$108 | 2,347 | $70 | 10 | - | - | - | - | - | - |
$108 2,347 kWh |
$70 10 kW-months/year |
- - Tgal |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 3.4151 MINIMIZE WATER USAGE |
Savings: $503 Cost: $1,705 |
- | - | - | - | $503 | 102,960 | - | - | - | - |
- - kWh |
- - kW-months/year |
$503 102,960 Tgal |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 4.441 INSTALL AUTOMATIC PACKING EQUIPMENT |
Savings: $57,853 Cost: $25,000 |
- | - | - | - | - | - | $57,853 | - | - | - |
- - kWh |
- - kW-months/year |
- - Tgal |
$57,853 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 4.521 CLEAR AND RENT EXISTING SPACE |
Savings: $48,656 Cost: $3,000 |
- | - | - | - | - | - | $48,656 | - | - | - |
- - kWh |
- - kW-months/year |
- - Tgal |
$48,656 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
11: 4.447 AUTOMATE PAYROLL SYSTEM |
Savings: $6,760 Cost: $1,760 |
- | - | - | - | - | - | $6,760 | - | - | - |
- - kWh |
- - kW-months/year |
- - Tgal |
$6,760 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $117,789 Cost: $38,767 |
$2,969 | 64,812 | $718 | 99 | $503 | 102,960 | $113,269 | - | $330 | - | $2,969 64,812 kWh |
$718 99 kW-months/year |
$503 102,960 Tgal |
$113,269 - $ |
$330 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $6,760 Cost: $1,760 |
- | - | - | - | - | - | $6,760 | - | - | - | - - kWh |
- - kW-months/year |
- - Tgal |
$6,760 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | Tgal | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Water Disposal | Administrative Changes | One-time Revenue or Avoided Cost | Electricity Usage | Electricity Demand | Water Disposal | Administrative Changes | One-time Revenue or Avoided Cost |