Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Bradley University |
---|---|
Assessment Year | 2001 |
Principal Product | Ball and Roller Bearings |
NAICS | n/a |
SIC | 3562 - Ball And Roller Bearings |
Sales | $50,000,000-$100,000,000 |
# of Employees | 200 |
Plant Area (Sq.Ft.) | 213,000 |
Annual Production | 50,000,000 Pounds |
Production Hrs. Annual | 7,488 |
Location (State) | IL |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $854,857 | 18,067,488 | kWh | $0.05 |
Electricity Demand | $116,666 | 34,301 | kW-months/year | $3.40 |
Electricity Fees | $51,216 | - | $ | - |
Natural Gas | $48,169 | 11,467 | MMBtu | $4.20 |
TOTAL ENERGY COSTS | $1,093,790 | |||
RECOMMENDED SAVINGS* | $70,917 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $838 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | One-time Revenue or Avoided Cost | Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | One-time Revenue or Avoided Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | Tgal | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $23,060 Cost: $28,920 |
$21,226 | 448,771 | $1,834 | 539 | - | - | - | - | - | - |
$21,226 448,771 kWh |
$1,834 539 kW-months/year |
- - MMBtu |
- - Tgal |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $15,876 Cost: $16,455 |
- | - | - | - | $15,876 | 4,157 | - | - | - | - |
- - kWh |
- - kW-months/year |
$15,876 4,157 MMBtu |
- - Tgal |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $5,419 Cost: $7,120 |
$4,891 | 103,409 | $528 | 155 | - | - | - | - | - | - |
$4,891 103,409 kWh |
$528 155 kW-months/year |
- - MMBtu |
- - Tgal |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7231 USE RADIANT HEATER FOR SPOT HEATING |
Savings: $4,255 Cost: $4,000 |
- | - | - | - | $4,255 | 1,114 | - | - | - | - |
- - kWh |
- - kW-months/year |
$4,255 1,114 MMBtu |
- - Tgal |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $3,191 Cost: $1,200 |
$2,738 | 57,878 | $453 | 133 | - | - | - | - | - | - |
$2,738 57,878 kWh |
$453 133 kW-months/year |
- - MMBtu |
- - Tgal |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $2,345 Cost: $1,000 |
$2,103 | 44,454 | $242 | 71 | - | - | - | - | - | - |
$2,103 44,454 kWh |
$242 71 kW-months/year |
- - MMBtu |
- - Tgal |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $2,269 Cost: $1,500 |
- | - | - | - | $2,269 | 594 | - | - | - | - |
- - kWh |
- - kW-months/year |
$2,269 594 MMBtu |
- - Tgal |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $838 Cost: $400 |
$751 | 15,864 | $87 | 26 | - | - | - | - | - | - |
$751 15,864 kWh |
$87 26 kW-months/year |
- - MMBtu |
- - Tgal |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $559 Cost: $541 |
$283 | 5,992 | $28 | 8 | - | - | - | - | $248 | - |
$283 5,992 kWh |
$28 8 kW-months/year |
- - MMBtu |
- - Tgal |
$248 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 3.3131 USE EVAPORATION TO CONCENTRATE MATERIAL |
Savings: $13,105 Cost: $27,000 |
- | - | - | - | - | - | $13,105 | 166,320 | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$13,105 166,320 Tgal |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $70,917 Cost: $88,136 |
$31,992 | 676,368 | $3,172 | 932 | $22,400 | 5,865 | $13,105 | 166,320 | $248 | - | $31,992 676,368 kWh |
$3,172 932 kW-months/year |
$22,400 5,865 MMBtu |
$13,105 166,320 Tgal |
$248 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $838 Cost: $400 |
$751 | 15,864 | $87 | 26 | - | - | - | - | - | - | $751 15,864 kWh |
$87 26 kW-months/year |
- - MMBtu |
- - Tgal |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | Tgal | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | One-time Revenue or Avoided Cost | Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | One-time Revenue or Avoided Cost |