Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Bradley University |
---|---|
Assessment Year | 2002 |
Principal Product | Industrial Metal Fasteners |
NAICS | n/a |
SIC | 3452 - Bolts, Nuts, Rivets, And Washers |
Sales | $10,000,000-$50,000,000 |
# of Employees | 128 |
Plant Area (Sq.Ft.) | 500,000 |
Annual Production | 450,000,000 Pieces |
Production Hrs. Annual | 8,760 |
Location (State) | IL |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $293,971 | 8,294,040 | kWh | $0.04 |
Electricity Demand | $203,299 | 18,554 | kW-months/year | $10.96 |
Electricity Fees | $360 | - | $ | - |
Natural Gas | $737,628 | 118,486 | MMBtu | $6.23 |
TOTAL ENERGY COSTS | $1,303,696 | |||
RECOMMENDED SAVINGS* | $171,285 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Other Liquid (non-haz) | Administrative Changes | One-time Revenue or Avoided Cost | Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Other Liquid (non-haz) | Administrative Changes | One-time Revenue or Avoided Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | Tgal | $ | gal | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7231 USE RADIANT HEATER FOR SPOT HEATING |
Savings: $90,110 Cost: $47,000 |
- | - | - | - | $90,110 | 13,632 | - | - | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$90,110 13,632 MMBtu |
- - Tgal |
- - gal |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.2426 USE WASTE HEAT FROM FLUE GASES TO HEAT SPACE CONDITIONING AIR |
Savings: $10,572 Cost: $25,000 |
- | - | - | - | $10,572 | 1,599 | - | - | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$10,572 1,599 MMBtu |
- - Tgal |
- - gal |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.1222 INSTALL TURBULATORS |
Savings: $7,093 Cost: $1,200 |
- | - | - | - | $7,093 | 1,073 | - | - | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$7,093 1,073 MMBtu |
- - Tgal |
- - gal |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4314 USE SYNTHETIC LUBRICANT |
Savings: $6,166 Cost: $3,000 |
$3,257 | 91,993 | $2,909 | 265 | - | - | - | - | - | - | - | - | - | - |
$3,257 91,993 kWh |
$2,909 265 kW-months/year |
- - MMBtu |
- - Tgal |
- - gal |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $5,720 Cost: $14,230 |
$3,395 | 95,911 | $2,325 | 212 | - | - | - | - | - | - | - | - | - | - |
$3,395 95,911 kWh |
$2,325 212 kW-months/year |
- - MMBtu |
- - Tgal |
- - gal |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.1213 DIRECT WARMEST AIR TO COMBUSTION INTAKE |
Savings: $4,357 Cost: $6,000 |
- | - | - | - | $4,357 | 659 | - | - | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$4,357 659 MMBtu |
- - Tgal |
- - gal |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $1,945 Cost: $2,300 |
$1,028 | 29,079 | $917 | 84 | - | - | - | - | - | - | - | - | - | - |
$1,028 29,079 kWh |
$917 84 kW-months/year |
- - MMBtu |
- - Tgal |
- - gal |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $1,490 Cost: $1,350 |
$405 | 11,423 | $1,085 | 99 | - | - | - | - | - | - | - | - | - | - |
$405 11,423 kWh |
$1,085 99 kW-months/year |
- - MMBtu |
- - Tgal |
- - gal |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $1,068 Cost: $2,150 |
$518 | 14,640 | $218 | 20 | - | - | - | - | - | - | - | - | $332 | - |
$518 14,640 kWh |
$218 20 kW-months/year |
- - MMBtu |
- - Tgal |
- - gal |
- - $ |
$332 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $550 Cost: $540 |
$212 | 5,992 | $90 | 8 | - | - | - | - | - | - | - | - | $248 | - |
$212 5,992 kWh |
$90 8 kW-months/year |
- - MMBtu |
- - Tgal |
- - gal |
- - $ |
$248 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
11: 3.3131 USE EVAPORATION TO CONCENTRATE MATERIAL |
Savings: $27,967 Cost: $10,000 |
- | - | - | - | - | - | - | - | $27,967 | - | - | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - Tgal |
$27,967 - gal |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
12: 3.4115 RECOVER AND REUSE COOLING WATER |
Savings: $3,392 Cost: $12,000 |
- | - | - | - | - | - | $3,392 | 2,221,440 | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$3,392 2,221,440 Tgal |
- - gal |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
13: 4.821 PAY BILLS ON TIME TO AVOID LATE FEES |
Savings: $10,555 Cost: - |
- | - | - | - | - | - | - | - | - | - | $10,555 | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - Tgal |
- - gal |
$10,555 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
14: 3.5316 CONTRACT A WOOD PALLET RECYCLING COMPANY |
Savings: $300 Cost: $500 |
- | - | - | - | - | - | - | - | - | - | - | - | $300 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - Tgal |
- - gal |
- - $ |
$300 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $171,285 Cost: $125,270 |
$8,815 | 249,038 | $7,544 | 688 | $112,132 | 16,963 | $3,392 | 2,221,440 | $27,967 | - | $10,555 | - | $880 | - | $8,815 249,038 kWh |
$7,544 688 kW-months/year |
$112,132 16,963 MMBtu |
$3,392 2,221,440 Tgal |
$27,967 - gal |
$10,555 - $ |
$880 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - | - | - | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - MMBtu |
- - Tgal |
- - gal |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | Tgal | $ | gal | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Other Liquid (non-haz) | Administrative Changes | One-time Revenue or Avoided Cost | Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Other Liquid (non-haz) | Administrative Changes | One-time Revenue or Avoided Cost |