IAC Assessment: BD0265
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: BD0265
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Bradley University
Assessment Year 2004
Principal Product Metal Industrial Fasteners for Automotive Industry
NAICS 332722 - Bolt, Nut, Screw, Rivet, and Washer Manufacturing
SIC 3452 - Bolts, Nuts, Rivets, And Washers
Sales $10,000,000-$50,000,000
# of Employees 186
Plant Area (Sq.Ft.) 116,000
Annual Production 17,000,000 Pounds
Production Hrs. Annual 5,460
Location (State) IL
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $227,048 7,993,537 kWh $0.03
Electricity Demand $78,492 18,882 kW-months/year $4.16
Natural Gas $128,353 26,251 MMBtu $4.89
TOTAL ENERGY COSTS $440,017
RECOMMENDED SAVINGS* $63,300 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* -
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas Water Disposal Solid Waste (non-haz) Personnel Changes Primary Raw Material Electricity Usage Electricity Demand Natural Gas Water Disposal Solid Waste (non-haz) Personnel Changes Primary Raw Material
$ kWh $ kW-months/year $ MMBtu $ Tgal $ lb $ $ $ $
01: 2.7231 USE RADIANT HEATER FOR SPOT HEATING Savings:
$27,949
Cost:
$4,200
- - - - $27,949 5,159 - - - - - - - - -
-
kWh
-
-
kW-months/year
$27,949
5,159
MMBtu
-
-
Tgal
-
-
lb
-
-
$
-
-
$
02: 2.2531 RE-SIZE CHARGING OPENINGS OR ADD MOVABLE COVER OR DOOR Savings:
$3,335
Cost:
$20,000
- - - - $3,335 616 - - - - - - - - -
-
kWh
-
-
kW-months/year
$3,335
616
MMBtu
-
-
Tgal
-
-
lb
-
-
$
-
-
$
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$5,398
Cost:
$2,861
$4,101 141,902 $1,297 312 - - - - - - - - - - $4,101
141,902
kWh
$1,297
312
kW-months/year
-
-
MMBtu
-
-
Tgal
-
-
lb
-
-
$
-
-
$
04: 2.4314 USE SYNTHETIC LUBRICANT Savings:
$4,332
Cost:
$1,650
$3,291 113,886 $1,041 250 - - - - - - - - - - $3,291
113,886
kWh
$1,041
250
kW-months/year
-
-
MMBtu
-
-
Tgal
-
-
lb
-
-
$
-
-
$
05: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS Savings:
$2,701
Cost:
$1,200
$2,052 70,988 $649 156 - - - - - - - - - - $2,052
70,988
kWh
$649
156
kW-months/year
-
-
MMBtu
-
-
Tgal
-
-
lb
-
-
$
-
-
$
06: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED Savings:
$2,323
Cost:
-
$1,764 61,044 $559 134 - - - - - - - - - - $1,764
61,044
kWh
$559
134
kW-months/year
-
-
MMBtu
-
-
Tgal
-
-
lb
-
-
$
-
-
$
07: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$1,397
Cost:
$2,200
$728 25,182 $230 55 - - - - - - $164 - $275 - $728
25,182
kWh
$230
55
kW-months/year
-
-
MMBtu
-
-
Tgal
-
-
lb
$164
-
$
$275
-
$
08: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$782
Cost:
$602
$289 9,959 $57 14 - - - - - - $258 - $178 - $289
9,959
kWh
$57
14
kW-months/year
-
-
MMBtu
-
-
Tgal
-
-
lb
$258
-
$
$178
-
$
09: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$660
Cost:
$424
$173 5,972 $104 25 - - - - - - $124 - $259 - $173
5,972
kWh
$104
25
kW-months/year
-
-
MMBtu
-
-
Tgal
-
-
lb
$124
-
$
$259
-
$
10: 2.7135 INSTALL OCCUPANCY SENSORS Savings:
$393
Cost:
$330
$274 9,469 $119 29 - - - - - - - - - - $274
9,469
kWh
$119
29
kW-months/year
-
-
MMBtu
-
-
Tgal
-
-
lb
-
-
$
-
-
$
11: 3.3131 USE EVAPORATION TO CONCENTRATE MATERIAL Savings:
$13,608
Cost:
$10,512
- - - - - - $13,608 95,850 - - - - - - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
$13,608
95,850
Tgal
-
-
lb
-
-
$
-
-
$
12: 3.4111 USE CLOSED CYCLE PROCESS TO MINIMIZE WASTE WATER PRODUCTION Savings:
$307
Cost:
-
- - - - - - $43 6,540 $264 - - - - - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
$43
6,540
Tgal
$264
-
lb
-
-
$
-
-
$
13: 2.3137 USE POWER DURING OFF-PEAK PERIODS Savings:
$115
Cost:
-
- - $115 29 - - - - - - - - - - -
-
kWh
$115
29
kW-months/year
-
-
MMBtu
-
-
Tgal
-
-
lb
-
-
$
-
-
$
TOTAL RECOMMENDED Savings:
$63,300
Cost:
$43,979
$12,672 438,402 $4,171 1,004 $31,284 5,774 $13,651 102,390 $264 - $546 - $712 - $12,672
438,402
kWh
$4,171
1,004
kW-months/year
$31,284
5,774
MMBtu
$13,651
102,390
Tgal
$264
-
lb
$546
-
$
$712
-
$
TOTAL IMPLEMENTED Savings:
-
Cost:
-
- - - - - - - - - - - - - - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
Tgal
-
-
lb
-
-
$
-
-
$
Savings
Cost
$ kWh $ kW-months/year $ MMBtu $ Tgal $ lb $ $ $ $
Electricity Usage Electricity Demand Natural Gas Water Disposal Solid Waste (non-haz) Personnel Changes Primary Raw Material Electricity Usage Electricity Demand Natural Gas Water Disposal Solid Waste (non-haz) Personnel Changes Primary Raw Material