Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Bradley University |
---|---|
Assessment Year | 2008 |
Principal Product | Fasteners |
NAICS | 332722 - Bolt, Nut, Screw, Rivet, and Washer Manufacturing |
SIC | 3452 - Bolts, Nuts, Rivets, And Washers |
Sales | $10,000,000-$50,000,000 |
# of Employees | 190 |
Plant Area (Sq.Ft.) | 145,000 |
Annual Production | 1,300,000,000 Pieces |
Production Hrs. Annual | 4,992 |
Location (State) | IL |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $752,679 | 17,271,036 | kWh | $0.04 |
Electricity Demand | $315,446 | 24,567 | kW-months/year | $12.84 |
Electricity Fees | $264,894 | - | $ | - |
Natural Gas | $369,551 | 51,813 | MMBtu | $7.13 |
TOTAL ENERGY COSTS | $1,733,585 | |||
RECOMMENDED SAVINGS* | $332,665 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Personnel Changes | Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Personnel Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | Tgal | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $19,613 Cost: $24,066 |
$12,621 | 289,478 | $6,992 | 545 | - | - | - | - | - | - |
$12,621 289,478 kWh |
$6,992 545 kW-months/year |
- - MMBtu |
- - Tgal |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $1,392 Cost: $2,026 |
$636 | 14,587 | $756 | 59 | - | - | - | - | - | - |
$636 14,587 kWh |
$756 59 kW-months/year |
- - MMBtu |
- - Tgal |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $9,758 Cost: $2,001 |
- | - | - | - | $9,758 | 1,393 | - | - | - | - |
- - kWh |
- - kW-months/year |
$9,758 1,393 MMBtu |
- - Tgal |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $5,081 Cost: $2 |
$2,628 | 60,280 | $2,453 | 191 | - | - | - | - | - | - |
$2,628 60,280 kWh |
$2,453 191 kW-months/year |
- - MMBtu |
- - Tgal |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $142,941 Cost: $1,401 |
$67,010 | 1,468,123 | $75,931 | 3,577 | - | - | - | - | - | - |
$67,010 1,468,123 kWh |
$75,931 3,577 kW-months/year |
- - MMBtu |
- - Tgal |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7231 USE RADIANT HEATER FOR SPOT HEATING |
Savings: $7,689 Cost: $5,001 |
- | - | - | - | $7,689 | 1,079 | - | - | - | - |
- - kWh |
- - kW-months/year |
$7,689 1,079 MMBtu |
- - Tgal |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.1221 REPLACE OBSOLETE BURNERS WITH MORE EFFICIENT ONES |
Savings: $50,882 Cost: $42,001 |
- | - | - | - | $50,882 | 7,259 | - | - | - | - |
- - kWh |
- - kW-months/year |
$50,882 7,259 MMBtu |
- - Tgal |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $9,743 Cost: $7,844 |
$6,619 | 151,813 | $3,124 | 243 | - | - | - | - | - | - |
$6,619 151,813 kWh |
$3,124 243 kW-months/year |
- - MMBtu |
- - Tgal |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.2614 USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING |
Savings: $54,402 Cost: $12,001 |
- | - | - | - | - | - | $54,402 | 10,929,485 | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$54,402 10,929,485 Tgal |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 2.7447 INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS |
Savings: $31,164 Cost: $7,000 |
- | - | - | - | - | - | - | - | $31,164 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - Tgal |
$31,164 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $332,665 Cost: $103,343 |
$89,514 | 1,984,281 | $89,256 | 4,615 | $68,329 | 9,731 | $54,402 | 10,929,485 | $31,164 | - | $89,514 1,984,281 kWh |
$89,256 4,615 kW-months/year |
$68,329 9,731 MMBtu |
$54,402 10,929,485 Tgal |
$31,164 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - MMBtu |
- - Tgal |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | Tgal | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Personnel Changes | Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Personnel Changes |