Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Bradley University |
---|---|
Assessment Year | 2010 |
Principal Product | Steel Prodcuts |
NAICS | 332312 - Fabricated Structural Metal Manufacturing |
SIC | 3441 - Fabricated Structural Metal |
Sales | $1,000,000-$5,000,000 |
# of Employees | 69 |
Plant Area (Sq.Ft.) | 200,000 |
Annual Production | 52,362,675 Pounds |
Production Hrs. Annual | 6,240 |
Location (State) | IL |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $117,713 | 1,757,434 | kWh | $0.07 |
Electricity Demand | $39,784 | 7,428 | kW-months/year | $5.36 |
Electricity Fees | $10,605 | - | $ | - |
Natural Gas | $35,679 | 3,778 | MMBtu | $9.44 |
TOTAL ENERGY COSTS | $203,781 | |||
RECOMMENDED SAVINGS* | $57,060 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $30,334 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7231 USE RADIANT HEATER FOR SPOT HEATING |
Savings: $18,738 Cost: $7,700 |
$88 | 1,327 | $69 | 13 | $18,581 | 1,531 | - | - | - | - |
$88 1,327 kWh |
$69 13 kW-months/year |
$18,581 1,531 MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $17,099 Cost: $59,000 |
$15,012 | 226,418 | $2,332 | 435 | - | - | $246 | - | $(-491) | - |
$15,012 226,418 kWh |
$2,332 435 kW-months/year |
- - MMBtu |
$246 - $ |
$(-491) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $5,855 Cost: $4,900 |
$5,160 | 77,828 | $818 | 153 | - | - | $122 | - | $(-245) | - |
$5,160 77,828 kWh |
$818 153 kW-months/year |
- - MMBtu |
$122 - $ |
$(-245) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $5,181 Cost: $10 |
$4,201 | 63,371 | $980 | 183 | - | - | - | - | - | - |
$4,201 63,371 kWh |
$980 183 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $5,027 Cost: $10,100 |
$4,076 | 61,476 | $951 | 177 | - | - | - | - | - | - |
$4,076 61,476 kWh |
$951 177 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $2,199 Cost: $8,511 |
$1,783 | 26,888 | $416 | 78 | - | - | - | - | - | - |
$1,783 26,888 kWh |
$416 78 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4314 USE SYNTHETIC LUBRICANT |
Savings: $1,752 Cost: $900 |
$1,420 | 21,413 | $332 | 62 | - | - | - | - | - | - |
$1,420 21,413 kWh |
$332 62 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $826 Cost: $1,200 |
$670 | 10,100 | $156 | 29 | - | - | - | - | - | - |
$670 10,100 kWh |
$156 29 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $383 Cost: $300 |
$221 | 3,329 | $24 | 5 | - | - | $58 | - | $80 | - |
$221 3,329 kWh |
$24 5 kW-months/year |
- - MMBtu |
$58 - $ |
$80 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $57,060 Cost: $92,621 |
$32,631 | 492,150 | $6,078 | 1,135 | $18,581 | 1,531 | $426 | - | $(-656) | - | $32,631 492,150 kWh |
$6,078 1,135 kW-months/year |
$18,581 1,531 MMBtu |
$426 - $ |
$(-656) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $30,334 Cost: $72,421 |
$26,156 | 394,505 | $4,546 | 849 | - | - | $368 | - | $(-736) | - | $26,156 394,505 kWh |
$4,546 849 kW-months/year |
- - MMBtu |
$368 - $ |
$(-736) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Ancillary Material Cost |