Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Bradley University |
---|---|
Assessment Year | 2011 |
Principal Product | Low carbon steel balls |
NAICS | 332991 - Ball and Roller Bearing Manufacturing |
SIC | 3562 - Ball And Roller Bearings |
Sales | $5,000,000-$10,000,000 |
# of Employees | 15 |
Plant Area (Sq.Ft.) | 90,000 |
Annual Production | 120,000,000 Pieces |
Production Hrs. Annual | 6,240 |
Location (State) | IL |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $113,737 | 1,961,477 | kWh | $0.06 |
Electricity Demand | $25,963 | 4,334 | kW-months/year | $5.99 |
Electricity Fees | $12,216 | - | $ | - |
Natural Gas | $218,989 | 47,350 | MMBtu | $4.62 |
TOTAL ENERGY COSTS | $370,905 | |||
RECOMMENDED SAVINGS* | $81,721 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $38,744 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Electricity Usage | Electricity Demand | Natural Gas | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.2414 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT |
Savings: $27,912 Cost: $30,000 |
$(-1,592) | (-28,080) | $(-431) | (-72) | $29,935 | 6,110 |
$(-1,592) (-28,080) kWh |
$(-431) (-72) kW-months/year |
$29,935 6,110 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.1221 REPLACE OBSOLETE BURNERS WITH MORE EFFICIENT ONES |
Savings: $15,065 Cost: $27,000 |
- | - | - | - | $15,065 | 3,309 |
- - kWh |
- - kW-months/year |
$15,065 3,309 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7231 USE RADIANT HEATER FOR SPOT HEATING |
Savings: $12,072 Cost: $12,600 |
- | - | - | - | $12,072 | 2,613 |
- - kWh |
- - kW-months/year |
$12,072 2,613 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $7,389 Cost: $20 |
$6,141 | 108,307 | $1,248 | 208 | - | - |
$6,141 108,307 kWh |
$1,248 208 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $7,217 Cost: $1,600 |
$5,999 | 105,800 | $1,218 | 203 | - | - |
$5,999 105,800 kWh |
$1,218 203 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $6,214 Cost: $10,450 |
$5,165 | 91,094 | $1,049 | 175 | - | - |
$5,165 91,094 kWh |
$1,049 175 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $3,602 Cost: $2,039 |
$2,993 | 52,839 | $609 | 102 | - | - |
$2,993 52,839 kWh |
$609 102 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $2,250 Cost: $1,058 |
$1,870 | 32,979 | $380 | 63 | - | - |
$1,870 32,979 kWh |
$380 63 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $81,721 Cost: $84,767 |
$20,576 | 362,939 | $4,073 | 680 | $57,072 | 12,032 | $20,576 362,939 kWh |
$4,073 680 kW-months/year |
$57,072 12,032 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $38,744 Cost: $27,767 |
$22,168 | 391,019 | $4,504 | 752 | $12,072 | 2,613 | $22,168 391,019 kWh |
$4,504 752 kW-months/year |
$12,072 2,613 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Electricity Usage | Electricity Demand | Natural Gas |