IAC Assessment: BD0450
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: BD0450
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Bradley University
Assessment Year 2014
Principal Product Plastic resin pellets
NAICS 488991 - Packing and Crating
SIC 4783 - Packing And Crating
Sales $100,000,000-$500,000,000
# of Employees 250
Plant Area (Sq.Ft.) 323,700
Annual Production 0 Units
Production Hrs. Annual 5,200
Location (State) IL
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $281,480 2,663,579 kWh $0.11
Natural Gas $120,525 14,142 MMBtu $8.52
LPG $59,953 2,910 MMBtu $20.60
Fuel Oil #2 $325,204 13,515 MMBtu $24.06
Other Gas $22,891 861 MMBtu $26.59
TOTAL ENERGY COSTS $810,053
RECOMMENDED SAVINGS* $47,546 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $7,471
#|Description Savings
Cost
Status Electricity Usage Natural Gas Personnel Changes Ancillary Material Cost Electricity Usage Natural Gas Personnel Changes Ancillary Material Cost
$ kWh $ MMBtu $ $ $ $
01: 2.7231 USE RADIANT HEATER FOR SPOT HEATING Savings:
$19,966
Cost:
$27,000
- - $19,966 2,343 - - - - -
-
kWh
$19,966
2,343
MMBtu
-
-
$
-
-
$
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$16,234
Cost:
$24,940
$15,981 151,204 - - $119 - $134 - $15,981
151,204
kWh
-
-
MMBtu
$119
-
$
$134
-
$
03: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS Savings:
$2,837
Cost:
$1,000
$2,837 26,844 - - - - - - $2,837
26,844
kWh
-
-
MMBtu
-
-
$
-
-
$
04: 2.4321 UPGRADE OBSOLETE EQUIPMENT Savings:
$2,486
Cost:
$20
$2,486 23,522 - - - - - - $2,486
23,522
kWh
-
-
MMBtu
-
-
$
-
-
$
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$2,148
Cost:
$2,850
$2,105 19,918 - - $12 - $31 - $2,105
19,918
kWh
-
-
MMBtu
$12
-
$
$31
-
$
06: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$1,909
Cost:
$1,025
$1,372 12,982 - - $225 - $312 - $1,372
12,982
kWh
-
-
MMBtu
$225
-
$
$312
-
$
07: 2.7134 USE PHOTOCELL CONTROLS Savings:
$777
Cost:
$450
$659 6,234 - - $104 - $14 - $659
6,234
kWh
-
-
MMBtu
$104
-
$
$14
-
$
08: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS Savings:
$461
Cost:
$320
$461 4,357 - - - - - - $461
4,357
kWh
-
-
MMBtu
-
-
$
-
-
$
09: 2.7135 INSTALL OCCUPANCY SENSORS Savings:
$406
Cost:
$750
$406 3,840 - - - - - - $406
3,840
kWh
-
-
MMBtu
-
-
$
-
-
$
10: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$322
Cost:
$143
$254 2,402 - - $19 - $49 - $254
2,402
kWh
-
-
MMBtu
$19
-
$
$49
-
$
TOTAL RECOMMENDED Savings:
$47,546
Cost:
$58,498
$26,561 251,303 $19,966 2,343 $479 - $540 - $26,561
251,303
kWh
$19,966
2,343
MMBtu
$479
-
$
$540
-
$
TOTAL IMPLEMENTED Savings:
$7,471
Cost:
$3,870
$7,428 70,284 - - $12 - $31 - $7,428
70,284
kWh
-
-
MMBtu
$12
-
$
$31
-
$
Savings
Cost
$ kWh $ MMBtu $ $ $ $
Electricity Usage Natural Gas Personnel Changes Ancillary Material Cost Electricity Usage Natural Gas Personnel Changes Ancillary Material Cost