Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Clemson University |
---|---|
Assessment Year | 2019 |
Principal Product | pharmaceuticals |
NAICS | 325411 - Medicinal and Botanical Manufacturing |
SIC | 2834 - Pharmaceutical Preparations |
Sales | $10,000,000-$50,000,000 |
# of Employees | 700 |
Plant Area (Sq.Ft.) | 230,000 |
Annual Production | 60,000,000 Pieces |
Production Hrs. Annual | 6,240 |
Location (State) | SC |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $1,042,384 | 31,654,378 | kWh | $0.03 |
Electricity Demand | $537,551 | 102,872 | kW-months/year | $5.23 |
Electricity Fees | $58,766 | - | $ | - |
Natural Gas | $831,861 | 155,174 | MMBtu | $5.36 |
TOTAL ENERGY COSTS | $2,470,562 | |||
RECOMMENDED SAVINGS* | $91,784 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Electricity Usage | Electricity Demand | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $2,099 Cost: $450 |
$845 | 24,850 | $1,254 | 119 |
$845 24,850 kWh |
$1,254 119 kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $74,869 Cost: $246,400 |
$46,957 | 1,380,995 | $27,912 | 2,656 |
$46,957 1,380,995 kWh |
$27,912 2,656 kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.3137 USE POWER DURING OFF-PEAK PERIODS |
Savings: $14,816 Cost: $1,000 |
$13,325 | 319,111 | $1,491 | 2,406 |
$13,325 319,111 kWh |
$1,491 2,406 kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $91,784 Cost: $247,850 |
$61,127 | 1,724,956 | $30,657 | 5,181 | $61,127 1,724,956 kWh |
$30,657 5,181 kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - - kWh |
- - kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||