IAC Assessment: CL2011
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: CL2011
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Clemson University
Assessment Year 2020
Principal Product High quality Potable Water
NAICS 221310 - Water Supply and Irrigation Systems
SIC 4941 - Water Supply
Sales $50,000,000-$100,000,000
# of Employees 16
Plant Area (Sq.Ft.) 92,000
Annual Production 7,527,000 Thousand Gallons
Production Hrs. Annual 8,760
Location (State) SC
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $1,057,800 14,150,340 kWh $0.07
Electricity Demand $181,957 35,185 kW-months/year $5.17
TOTAL ENERGY COSTS $1,289,758
RECOMMENDED SAVINGS* $17,353 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $17,353
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Administrative Changes Electricity Usage Electricity Demand Administrative Changes
$ kWh $ kW-months/year $ $
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$4,964
Cost:
$3,933
$4,367 58,419 $597 115 - - $4,367
58,419
kWh
$597
115
kW-months/year
-
-
$
02: 2.7135 INSTALL OCCUPANCY SENSORS Savings:
$1,997
Cost:
$295
$1,997 26,720 - - - - $1,997
26,720
kWh
-
-
kW-months/year
-
-
$
03: 2.6212 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME Savings:
$587
Cost:
-
$587 7,849 - - - - $587
7,849
kWh
-
-
kW-months/year
-
-
$
04: 4.463 MODIFY FACILITY TO AVOID EXCESS MAINTENANCE COSTS Savings:
$7,830
Cost:
$4,500
- - - - $7,830 - -
-
kWh
-
-
kW-months/year
$7,830
-
$
05: 2.3131 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS Savings:
$1,975
Cost:
$400
- - $1,975 382 - - -
-
kWh
$1,975
382
kW-months/year
-
-
$
TOTAL RECOMMENDED Savings:
$17,353
Cost:
$9,128
$6,951 92,988 $2,572 497 $7,830 - $6,951
92,988
kWh
$2,572
497
kW-months/year
$7,830
-
$
TOTAL IMPLEMENTED Savings:
$17,353
Cost:
$9,128
$6,951 92,988 $2,572 497 $7,830 - $6,951
92,988
kWh
$2,572
497
kW-months/year
$7,830
-
$
Savings
Cost
$ kWh $ kW-months/year $ $
Electricity Usage Electricity Demand Administrative Changes Electricity Usage Electricity Demand Administrative Changes