Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Colorado State University |
---|---|
Assessment Year | 2002 |
Principal Product | Rifle scopes, spotting scopes, binoculars, and rifle scope base attachme |
NAICS | n/a |
SIC | 3827 - Optical Instruments And Lenses |
Sales | $10,000,000-$50,000,000 |
# of Employees | 85 |
Plant Area (Sq.Ft.) | 28,500 |
Annual Production | 36,400 Pieces |
Production Hrs. Annual | 4,680 |
Location (State) | CO |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $10,246 | 639,440 | kWh | $0.02 |
Electricity Demand | $32,550 | 2,510 | kW-months/year | $12.97 |
Electricity Fees | $192 | - | $ | - |
Natural Gas | $8,640 | 970 | MMBtu | $8.91 |
TOTAL ENERGY COSTS | $51,628 | |||
RECOMMENDED SAVINGS* | $4,705 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $4,705 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Personnel Changes | Administrative Changes | Electricity Usage | Electricity Demand | Personnel Changes | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.3191 USE DEMAND CONTROLLER OR LOAD SHEDDER |
Savings: $3,040 Cost: $7,000 |
- | - | $3,040 | 240 | - | - | - | - |
- - kWh |
$3,040 240 kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $1,250 Cost: $1,950 |
$540 | 32,800 | $1,070 | 84 | $(-360) | - | - | - |
$540 32,800 kWh |
$1,070 84 kW-months/year |
$(-360) - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $371 Cost: - |
$540 | 32,800 | $1,170 | 92 | $(-42) | - | $(-1,297) | - |
$540 32,800 kWh |
$1,170 92 kW-months/year |
$(-42) - $ |
$(-1,297) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $44 Cost: $44 |
$16 | 880 | $28 | 2 | - | - | - | - |
$16 880 kWh |
$28 2 kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $4,705 Cost: $8,994 |
$1,096 | 66,480 | $5,308 | 418 | $(-402) | - | $(-1,297) | - | $1,096 66,480 kWh |
$5,308 418 kW-months/year |
$(-402) - $ |
$(-1,297) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $4,705 Cost: $8,994 |
$1,096 | 66,480 | $5,308 | 418 | $(-402) | - | $(-1,297) | - | $1,096 66,480 kWh |
$5,308 418 kW-months/year |
$(-402) - $ |
$(-1,297) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Personnel Changes | Administrative Changes | Electricity Usage | Electricity Demand | Personnel Changes | Administrative Changes |