Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Colorado State University |
---|---|
Assessment Year | 2002 |
Principal Product | Pumps and compressors |
NAICS | n/a |
SIC | 3561 - Pumps And Pumping Equipment |
Sales | $50,000,000-$100,000,000 |
# of Employees | 310 |
Plant Area (Sq.Ft.) | 181,500 |
Annual Production | 50,000 Pieces |
Production Hrs. Annual | 2,730 |
Location (State) | CO |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $135,861 | 8,091,775 | kWh | $0.02 |
Electricity Demand | $238,333 | 32,521 | kW-months/year | $7.33 |
Electricity Fees | $1,652 | - | $ | - |
Natural Gas | $35,787 | 6,317 | MMBtu | $5.67 |
TOTAL ENERGY COSTS | $430,953 | |||
RECOMMENDED SAVINGS* | $22,202 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $4,300 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Other Liquid (haz) | Solid Waste (non-haz) | Personnel Changes | Administrative Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Other Liquid (haz) | Solid Waste (non-haz) | Personnel Changes | Administrative Changes | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | gal | $ | lb | $ | $ | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.3191 USE DEMAND CONTROLLER OR LOAD SHEDDER |
Savings: $7,510 Cost: $12,000 |
- | - | $7,510 | 900 | - | - | - | - | - | - | - | - | - | - |
- - kWh |
$7,510 900 kW-months/year |
- - gal |
- - lb |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $3,150 Cost: $540 |
$1,530 | 88,000 | $2,400 | 338 | - | - | - | - | $(-780) | - | - | - | - | - |
$1,530 88,000 kWh |
$2,400 338 kW-months/year |
- - gal |
- - lb |
$(-780) - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $432 Cost: $240 |
$204 | 11,740 | $228 | 32 | - | - | - | - | - | - | - | - | - | - |
$204 11,740 kWh |
$228 32 kW-months/year |
- - gal |
- - lb |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $680 Cost: - |
$1,410 | 80,700 | $2,860 | 356 | - | - | - | - | $(-137) | - | $(-3,453) | - | - | - |
$1,410 80,700 kWh |
$2,860 356 kW-months/year |
- - gal |
- - lb |
$(-137) - $ |
$(-3,453) - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4239 ELIMINATE OR REDUCE COMPRESSED AIR USAGE |
Savings: $1,240 Cost: $3,630 |
$310 | 17,900 | $930 | 111 | - | - | - | - | - | - | - | - | - | - |
$310 17,900 kWh |
$930 111 kW-months/year |
- - gal |
- - lb |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 3.5316 CONTRACT A WOOD PALLET RECYCLING COMPANY |
Savings: $4,890 Cost: - |
- | - | - | - | - | - | $15,600 | - | $(-10,710) | - | - | - | - | - |
- - kWh |
- - kW-months/year |
- - gal |
$15,600 - lb |
$(-10,710) - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 3.8142 DISTILL CONTAMINATED SOLVENTS FOR REUSE |
Savings: $4,300 Cost: $5,420 |
- | - | $(-160) | (-22) | $2,870 | 561 | - | - | - | - | - | - | $1,590 | - |
- - kWh |
$(-160) (-22) kW-months/year |
$2,870 561 gal |
- - lb |
- - $ |
- - $ |
$1,590 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $22,202 Cost: $21,830 |
$3,454 | 198,340 | $13,768 | 1,715 | $2,870 | 561 | $15,600 | - | $(-11,627) | - | $(-3,453) | - | $1,590 | - | $3,454 198,340 kWh |
$13,768 1,715 kW-months/year |
$2,870 561 gal |
$15,600 - lb |
$(-11,627) - $ |
$(-3,453) - $ |
$1,590 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $4,300 Cost: $5,420 |
- | - | $(-160) | (-22) | $2,870 | 561 | - | - | - | - | - | - | $1,590 | - | - - kWh |
$(-160) (-22) kW-months/year |
$2,870 561 gal |
- - lb |
- - $ |
- - $ |
$1,590 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | gal | $ | lb | $ | $ | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Other Liquid (haz) | Solid Waste (non-haz) | Personnel Changes | Administrative Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Other Liquid (haz) | Solid Waste (non-haz) | Personnel Changes | Administrative Changes | Ancillary Material Cost |