Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | South Dakota State |
---|---|
Assessment Year | 1997 |
Principal Product | Fixtures and Equipment for the Performing Arts |
NAICS | n/a |
SIC | 2531 - Public Building & Related Furniture |
Sales | $10,000,000-$50,000,000 |
# of Employees | 356 |
Plant Area (Sq.Ft.) | 260,365 |
Annual Production | 292,500 Pieces |
Production Hrs. Annual | 4,368 |
Location (State) | MN |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $84,367 | 3,058,617 | kWh | $0.03 |
Electricity Demand | $85,925 | 7,248 | kW-months/year | $11.85 |
Electricity Fees | $14,577 | - | $ | - |
Natural Gas | $19,052 | 9,125 | MMBtu | $2.09 |
LPG | $8,090 | 895 | MMBtu | $9.04 |
TOTAL ENERGY COSTS | $217,811 | |||
RECOMMENDED SAVINGS* | $542,879 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $9,219 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Other Liquid (haz) | Personnel Changes | Administrative Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Other Liquid (haz) | Personnel Changes | Administrative Changes | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | gal | $ | $ | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $4,501 Cost: $7,978 |
$2,010 | 71,805 | $2,491 | 210 | - | - | - | - | - | - | - | - | - | - |
$2,010 71,805 kWh |
$2,491 210 kW-months/year |
- - MMBtu |
- - gal |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $961 Cost: $1,250 |
$420 | 14,947 | $541 | 46 | - | - | - | - | - | - | - | - | - | - |
$420 14,947 kWh |
$541 46 kW-months/year |
- - MMBtu |
- - gal |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.3132 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS |
Savings: $3,757 Cost: $775 |
- | - | $3,757 | 317 | - | - | - | - | - | - | - | - | - | - |
- - kWh |
$3,757 317 kW-months/year |
- - MMBtu |
- - gal |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 3.8142 DISTILL CONTAMINATED SOLVENTS FOR REUSE |
Savings: $1,927 Cost: $6,000 |
$(-474) | 1,758 | - | - | - | - | $1,537 | 450 | $(-936) | - | - | - | $1,800 | - |
$(-474) 1,758 kWh |
- - kW-months/year |
- - MMBtu |
$1,537 450 gal |
$(-936) - $ |
- - $ |
$1,800 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 3.5111 FILTER AND REUSE HYDRAULIC OIL |
Savings: $300 Cost: $160 |
- | - | - | - | - | - | $300 | 300 | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$300 300 gal |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 4.211 CONSIDER USE / PURCHASE OF BULK MATERIALS WHERE POSSIBLE |
Savings: $505 Cost: $1,089 |
- | - | - | - | - | - | - | - | - | - | - | - | $505 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - gal |
- - $ |
- - $ |
$505 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 3.1191 CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS |
Savings: $89,400 Cost: - |
- | - | - | - | - | - | - | - | - | - | - | - | $89,400 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - gal |
- - $ |
- - $ |
$89,400 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 3.1191 CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS |
Savings: $441,528 Cost: $545,000 |
$(-23,922) | (-854,631) | $(-46,766) | (-3,943) | $(-7,784) | (-3,271) | - | - | - | - | $520,000 | - | - | - |
$(-23,922) (-854,631) kWh |
$(-46,766) (-3,943) kW-months/year |
$(-7,784) (-3,271) MMBtu |
- - gal |
- - $ |
$520,000 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $542,879 Cost: $562,252 |
$(-21,966) | (-766,121) | $(-39,977) | (-3,370) | $(-7,784) | (-3,271) | $1,837 | 750 | $(-936) | - | $520,000 | - | $91,705 | - | $(-21,966) (-766,121) kWh |
$(-39,977) (-3,370) kW-months/year |
$(-7,784) (-3,271) MMBtu |
$1,837 750 gal |
$(-936) - $ |
$520,000 - $ |
$91,705 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $9,219 Cost: $10,003 |
$2,430 | 86,752 | $6,789 | 573 | - | - | - | - | - | - | - | - | - | - | $2,430 86,752 kWh |
$6,789 573 kW-months/year |
- - MMBtu |
- - gal |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | gal | $ | $ | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Other Liquid (haz) | Personnel Changes | Administrative Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Other Liquid (haz) | Personnel Changes | Administrative Changes | Ancillary Material Cost |