Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Georgia Institute of Technology |
---|---|
Assessment Year | 1983 |
Principal Product | BLEACHING GREY GOODS |
NAICS | n/a |
SIC | 2261 - Finishing Plants, Cotton |
Sales | $50,000,000-$100,000,000 |
# of Employees | 500 |
Plant Area (Sq.Ft.) | 0 |
Annual Production | 17,500,000 Pounds |
Production Hrs. Annual | 6,000 |
Location (State) | GA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $412,383 | 8,048,945 | kWh | $0.05 |
Natural Gas | $548,490 | 104,013 | MMBtu | $5.27 |
Fuel Oil #6 | $106,202 | 23,256 | MMBtu | $4.57 |
TOTAL ENERGY COSTS | $1,067,075 | |||
RECOMMENDED SAVINGS* | $184,568 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Fuel Oil #6 | Electricity Usage | Natural Gas | Fuel Oil #6 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.5192 MODIFY TEXTILE DRYERS |
Savings: $74,410 Cost: $50,000 |
- | - | $71,248 | 13,552 | $3,162 | 788 |
- - kWh |
$71,248 13,552 MMBtu |
$3,162 788 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.5192 MODIFY TEXTILE DRYERS |
Savings: $67,354 Cost: $50,000 |
- | - | $60,825 | 11,243 | $6,529 | 1,207 |
- - kWh |
$60,825 11,243 MMBtu |
$6,529 1,207 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2135 REPAIR AND ELIMINATE STEAM LEAKS |
Savings: $8,427 Cost: $700 |
- | - | $6,611 | 1,317 | $1,816 | 393 |
- - kWh |
$6,611 1,317 MMBtu |
$1,816 393 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.3191 USE DEMAND CONTROLLER OR LOAD SHEDDER |
Savings: $6,370 Cost: $5,000 |
$6,370 | - | - | - | - | - |
$6,370 - kWh |
- - MMBtu |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $19,377 Cost: $18,463 |
$19,377 | 378,664 | - | - | - | - |
$19,377 378,664 kWh |
- - MMBtu |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.2414 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT |
Savings: $8,630 Cost: $5,999 |
- | - | $6,645 | 1,353 | $1,985 | 398 |
- - kWh |
$6,645 1,353 MMBtu |
$1,985 398 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $184,568 Cost: $130,162 |
$25,747 | 378,664 | $145,329 | 27,465 | $13,492 | 2,786 | $25,747 378,664 kWh |
$145,329 27,465 MMBtu |
$13,492 2,786 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - - kWh |
- - MMBtu |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Fuel Oil #6 | Electricity Usage | Natural Gas | Fuel Oil #6 |