Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Georgia Institute of Technology |
---|---|
Assessment Year | 1984 |
Principal Product | COTTON & SYNTHETIC YARN |
NAICS | n/a |
SIC | 2281 - Yarn Spinning Mills |
Sales | $10,000,000-$50,000,000 |
# of Employees | 334 |
Plant Area (Sq.Ft.) | 0 |
Annual Production | 15,800,000 Pounds |
Production Hrs. Annual | 7,200 |
Location (State) | GA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $753,045 | 15,716,882 | kWh | $0.05 |
Natural Gas | $80,836 | 16,810 | MMBtu | $4.81 |
TOTAL ENERGY COSTS | $833,881 | |||
RECOMMENDED SAVINGS* | $46,442 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $46,442 |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Electricity Usage | Natural Gas | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.1233 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO |
Savings: $5,150 Cost: $1,550 |
- | - | $5,150 | 1,110 |
- - kWh |
$5,150 1,110 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $6,482 Cost: $6,948 |
$6,482 | 137,163 | - | - |
$6,482 137,163 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $4,580 Cost: $5,660 |
$4,580 | 96,717 | - | - |
$4,580 96,717 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.6212 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME |
Savings: $1,720 Cost: - |
$1,720 | 35,170 | - | - |
$1,720 35,170 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.5194 REDESIGN PROCESS |
Savings: $10,210 Cost: $20,000 |
$10,210 | 325,322 | - | - |
$10,210 325,322 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.2223 ENHANCE SENSITIVITY OF TEMPERATURE CONTROL AND CUTOFF |
Savings: $18,300 Cost: $20,000 |
$18,300 | 583,236 | - | - |
$18,300 583,236 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $46,442 Cost: $54,158 |
$41,292 | 1,177,608 | $5,150 | 1,110 | $41,292 1,177,608 kWh |
$5,150 1,110 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $46,442 Cost: $54,158 |
$41,292 | 1,177,608 | $5,150 | 1,110 | $41,292 1,177,608 kWh |
$5,150 1,110 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Electricity Usage | Natural Gas |