Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Georgia Institute of Technology |
---|---|
Assessment Year | 1986 |
Principal Product | SPUN CARPET YARN |
NAICS | n/a |
SIC | 2281 - Yarn Spinning Mills |
Sales | $10,000,000-$50,000,000 |
# of Employees | 130 |
Plant Area (Sq.Ft.) | 0 |
Annual Production | 7,600,000 Pounds |
Production Hrs. Annual | 6,000 |
Location (State) | GA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $491,621 | 9,842,908 | kWh | $0.05 |
Natural Gas | $168,648 | 40,947 | MMBtu | $4.12 |
Fuel Oil #2 | $5,673 | 1,589 | MMBtu | $3.57 |
TOTAL ENERGY COSTS | $665,942 | |||
RECOMMENDED SAVINGS* | $263,636 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Fuel Oil #2 | Electricity Usage | Natural Gas | Fuel Oil #2 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $2,170 Cost: $2,356 |
$2,170 | 43,376 | - | - | - | - |
$2,170 43,376 kWh |
- - MMBtu |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $11,783 Cost: $32,572 |
$11,783 | 235,639 | - | - | - | - |
$11,783 235,639 kWh |
- - MMBtu |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $1,882 Cost: $2,790 |
$1,882 | 37,515 | - | - | - | - |
$1,882 37,515 kWh |
- - MMBtu |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.1233 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO |
Savings: $10,257 Cost: $1,000 |
- | - | $9,925 | 2,409 | $332 | 93 |
- - kWh |
$9,925 2,409 MMBtu |
$332 93 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $1,970 Cost: - |
$1,970 | 39,273 | - | - | - | - |
$1,970 39,273 kWh |
- - MMBtu |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7226 USE COMPUTER PROGRAMS TO OPTIMIZE HVAC PERFORMANCE |
Savings: $61,200 Cost: $10,000 |
$61,200 | 1,224,209 | - | - | - | - |
$61,200 1,224,209 kWh |
- - MMBtu |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4322 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES |
Savings: $37,018 Cost: $91,200 |
- | - | $35,815 | 8,693 | $1,203 | 337 |
- - kWh |
$35,815 8,693 MMBtu |
$1,203 337 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.4312 IMPROVE LUBRICATION PRACTICES |
Savings: $10,261 Cost: - |
$10,261 | 205,158 | - | - | - | - |
$10,261 205,158 kWh |
- - MMBtu |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.1333 CONVERT COMBUSTION EQUIPMENT TO BURN OIL |
Savings: $127,095 Cost: $28,000 |
- | - | $122,961 | 29,845 | $4,134 | 1,158 |
- - kWh |
$122,961 29,845 MMBtu |
$4,134 1,158 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $263,636 Cost: $167,918 |
$89,266 | 1,785,170 | $168,701 | 40,947 | $5,669 | 1,588 | $89,266 1,785,170 kWh |
$168,701 40,947 MMBtu |
$5,669 1,588 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - - kWh |
- - MMBtu |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Fuel Oil #2 | Electricity Usage | Natural Gas | Fuel Oil #2 |