Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Georgia Institute of Technology |
---|---|
Assessment Year | 1987 |
Principal Product | ROLLED METAL SHAPES |
NAICS | n/a |
SIC | 3442 - Metal Doors, Sash, And Trim |
Sales | $10,000,000-$50,000,000 |
# of Employees | 150 |
Plant Area (Sq.Ft.) | 0 |
Annual Production | 17,500,000 Pounds |
Production Hrs. Annual | 6,000 |
Location (State) | AL |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $185,956 | 2,403,869 | kWh | $0.08 |
Natural Gas | $37,452 | 6,991 | MMBtu | $5.36 |
TOTAL ENERGY COSTS | $223,408 | |||
RECOMMENDED SAVINGS* | $26,346 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $17,346 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Usage | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $5,760 Cost: $250 |
$5,760 | 77,960 |
$5,760 77,960 kWh |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4237 SUBSTITUTE COMPRESSED AIR COOLING WITH WATER OR AIR COOLING |
Savings: $9,000 Cost: $1,900 |
$9,000 | 123,388 |
$9,000 123,388 kWh |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2122 INSTALL / REPAIR INSULATION ON CONDENSATE LINES |
Savings: $381 Cost: $325 |
$381 | 5,275 |
$381 5,275 kWh |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $8,150 Cost: $2,500 |
$8,150 | 107,855 |
$8,150 107,855 kWh |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $2,656 Cost: $4,160 |
$2,656 | 34,291 |
$2,656 34,291 kWh |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $399 Cost: $793 |
$399 | 5,275 |
$399 5,275 kWh |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $26,346 Cost: $9,928 |
$26,346 | 354,044 | $26,346 354,044 kWh |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $17,346 Cost: $8,028 |
$17,346 | 230,656 | $17,346 230,656 kWh |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Usage |