Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Georgia Institute of Technology |
---|---|
Assessment Year | 1991 |
Principal Product | GRADUATION CAPS & GOWNS |
NAICS | n/a |
SIC | 2389 - Apparel And Accessories, Nec |
Sales | $10,000,000-$50,000,000 |
# of Employees | 218 |
Plant Area (Sq.Ft.) | 0 |
Annual Production | 1,400,000 Pieces |
Production Hrs. Annual | 4,500 |
Location (State) | SC |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $163,372 | 2,597,890 | kWh | $0.06 |
Natural Gas | $4,045 | 1,753 | MMBtu | $2.31 |
TOTAL ENERGY COSTS | $167,417 | |||
RECOMMENDED SAVINGS* | $29,108 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $29,108 |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Electricity Usage | Natural Gas | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $23,660 Cost: $2,037 |
$23,660 | 376,319 | - | - |
$23,660 376,319 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.6232 INSTALL SET-BACK TIMERS |
Savings: $1,390 Cost: $1,365 |
$1,390 | 21,981 | - | - |
$1,390 21,981 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $530 Cost: $1,840 |
$530 | 8,499 | - | - |
$530 8,499 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $2,609 Cost: $9,880 |
$2,609 | 41,325 | - | - |
$2,609 41,325 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.2135 REPAIR AND ELIMINATE STEAM LEAKS |
Savings: $696 Cost: $200 |
- | - | $696 | 313 |
- - kWh |
$696 313 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.2122 INSTALL / REPAIR INSULATION ON CONDENSATE LINES |
Savings: $223 Cost: $400 |
- | - | $223 | 100 |
- - kWh |
$223 100 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $29,108 Cost: $15,722 |
$28,189 | 448,124 | $919 | 413 | $28,189 448,124 kWh |
$919 413 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $29,108 Cost: $15,722 |
$28,189 | 448,124 | $919 | 413 | $28,189 448,124 kWh |
$919 413 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Electricity Usage | Natural Gas |