IAC Assessment: GT0510
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: GT0510
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Georgia Institute of Technology
Assessment Year 1993
Principal Product Specialty Chemicals
NAICS n/a
SIC 2899 - Chemical Preparations, Nec
Sales $50,000,000-$100,000,000
# of Employees 125
Plant Area (Sq.Ft.) 70,000
Annual Production 116,686,250 Pounds
Production Hrs. Annual 8,568
Location (State) GA
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $486,120 9,407,972 kWh $0.05
Natural Gas $791,775 216,332 MMBtu $3.66
Fuel Oil #2 $22,000 4,886 MMBtu $4.50
TOTAL ENERGY COSTS $1,299,895
RECOMMENDED SAVINGS* $173,560 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $157,800
#|Description Savings
Cost
Status Electricity Usage Natural Gas Electricity Usage Natural Gas
$ kWh $ MMBtu
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$4,220
Cost:
$9,990
$4,220 81,477 - - $4,220
81,477
kWh
-
-
MMBtu
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$700
Cost:
$930
$700 13,482 - - $700
13,482
kWh
-
-
MMBtu
03: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS Savings:
$1,250
Cost:
$500
$1,250 24,326 - - $1,250
24,326
kWh
-
-
MMBtu
04: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS Savings:
$1,880
Cost:
$5,260
$1,880 36,635 - - $1,880
36,635
kWh
-
-
MMBtu
05: 2.2121 INCREASE AMOUNT OF CONDENSATE RETURNED Savings:
$10,100
Cost:
$6,500
- - $10,100 2,760 -
-
kWh
$10,100
2,760
MMBtu
06: 2.1223 INSTALL SMALLER BOILER (INCREASE HIGH FIRE DUTY CYCLE) Savings:
$134,080
Cost:
$250,000
- - $134,080 36,634 -
-
kWh
$134,080
36,634
MMBtu
07: 2.2135 REPAIR AND ELIMINATE STEAM LEAKS Savings:
$20,590
Cost:
$2,400
- - $20,590 5,626 -
-
kWh
$20,590
5,626
MMBtu
08: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$740
Cost:
$2,160
$740 14,361 - - $740
14,361
kWh
-
-
MMBtu
TOTAL RECOMMENDED Savings:
$173,560
Cost:
$277,740
$8,790 170,281 $164,770 45,020 $8,790
170,281
kWh
$164,770
45,020
MMBtu
TOTAL IMPLEMENTED Savings:
$157,800
Cost:
$258,160
$3,130 60,961 $154,670 42,260 $3,130
60,961
kWh
$154,670
42,260
MMBtu
Savings
Cost
$ kWh $ MMBtu
Electricity Usage Natural Gas Electricity Usage Natural Gas