IAC Assessment: GT0689
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: GT0689
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Georgia Institute of Technology
Assessment Year 2000
Principal Product PVC Pipe And Vinyl Siding
NAICS n/a
SIC 3084 - Plastics Pipe
Sales $10,000,000-$50,000,000
# of Employees 255
Plant Area (Sq.Ft.) 983,000
Annual Production 51,983 Tons
Production Hrs. Annual 8,400
Location (State) GA
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $604,296 19,421,161 kWh $0.03
Electricity Demand $188,279 15,669 kW-months/year $12.02
Electricity Fees $47,865 - $ -
Natural Gas $5,429 878 MMBtu $6.18
TOTAL ENERGY COSTS $848,421
RECOMMENDED SAVINGS* $574,754 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* -
#|Description Savings
Cost
Status Electricity Usage Electricity Fees Other Liquid (non-haz) Personnel Changes Administrative Changes Ancillary Material Cost By-product Production Electricity Usage Electricity Fees Other Liquid (non-haz) Personnel Changes Administrative Changes Ancillary Material Cost By-product Production
$ kWh $ $ $ gal $ $ $ $ $ $ $ $
01: 2.3131 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS Savings:
$32,450
Cost:
-
- - - - - - - - $32,450 - - - - - -
-
kWh
-
-
$
-
-
gal
-
-
$
$32,450
-
$
-
-
$
-
-
$
02: 3.5112 REPROCESS SPENT OILS ON SITE FOR RE-USE Savings:
$9,458
Cost:
$8,900
- - - - $2,552 3,402 $(-300) - - - $7,206 - - - -
-
kWh
-
-
$
$2,552
3,402
gal
$(-300)
-
$
-
-
$
$7,206
-
$
-
-
$
03: 4.441 INSTALL AUTOMATIC PACKING EQUIPMENT Savings:
$72,000
Cost:
$112,000
- - - - - - $72,000 - - - - - - - -
-
kWh
-
-
$
-
-
gal
$72,000
-
$
-
-
$
-
-
$
-
-
$
04: 4.451 ADD ADDITIONAL PRODUCTION SHIFT Savings:
$336,000
Cost:
$225,000
- - - - - - - - - - - - $336,000 - -
-
kWh
-
-
$
-
-
gal
-
-
$
-
-
$
-
-
$
$336,000
-
$
05: 2.7111 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS Savings:
$1,495
Cost:
$2,000
$1,410 36,342 $85 - - - - - - - - - - - $1,410
36,342
kWh
$85
-
$
-
-
gal
-
-
$
-
-
$
-
-
$
-
-
$
06: 3.5212 REGRIND, REUSE, OR SELL SCRAP PLASTIC PARTS Savings:
$82,231
Cost:
-
$51,727 1,643,904 $3,104 - - - $27,400 - - - - - - - $51,727
1,643,904
kWh
$3,104
-
$
-
-
gal
$27,400
-
$
-
-
$
-
-
$
-
-
$
07: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$6,460
Cost:
$32,400
$6,094 201,641 $366 - - - - - - - - - - - $6,094
201,641
kWh
$366
-
$
-
-
gal
-
-
$
-
-
$
-
-
$
-
-
$
08: 2.7111 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS Savings:
$16,070
Cost:
$61,209
$15,163 519,930 $907 - - - - - - - - - - - $15,163
519,930
kWh
$907
-
$
-
-
gal
-
-
$
-
-
$
-
-
$
-
-
$
09: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS Savings:
$1,228
Cost:
-
$1,158 35,756 $70 - - - - - - - - - - - $1,158
35,756
kWh
$70
-
$
-
-
gal
-
-
$
-
-
$
-
-
$
-
-
$
10: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS Savings:
$17,362
Cost:
$72,500
$4,587 113,130 $275 - - - $12,500 - - - - - - - $4,587
113,130
kWh
$275
-
$
-
-
gal
$12,500
-
$
-
-
$
-
-
$
-
-
$
TOTAL RECOMMENDED Savings:
$574,754
Cost:
$514,009
$80,139 2,550,703 $4,807 - $2,552 3,402 $111,600 - $32,450 - $7,206 - $336,000 - $80,139
2,550,703
kWh
$4,807
-
$
$2,552
3,402
gal
$111,600
-
$
$32,450
-
$
$7,206
-
$
$336,000
-
$
TOTAL IMPLEMENTED Savings:
-
Cost:
-
- - - - - - - - - - - - - - -
-
kWh
-
-
$
-
-
gal
-
-
$
-
-
$
-
-
$
-
-
$
Savings
Cost
$ kWh $ $ $ gal $ $ $ $ $ $ $ $
Electricity Usage Electricity Fees Other Liquid (non-haz) Personnel Changes Administrative Changes Ancillary Material Cost By-product Production Electricity Usage Electricity Fees Other Liquid (non-haz) Personnel Changes Administrative Changes Ancillary Material Cost By-product Production