Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Hofstra Univ. |
---|---|
Assessment Year | 1995 |
Principal Product | Dental Equipment |
NAICS | n/a |
SIC | 3843 - Dental Equipment And Supplies |
Sales | $10,000,000-$50,000,000 |
# of Employees | 250 |
Plant Area (Sq.Ft.) | 80,000 |
Annual Production | 0 Units |
Production Hrs. Annual | 4,160 |
Location (State) | NY |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $156,135 | 1,111,665 | kWh | $0.14 |
Natural Gas | $5,400 | 653 | MMBtu | $8.27 |
Fuel Oil #2 | $15,307 | 2,449 | MMBtu | $6.25 |
TOTAL ENERGY COSTS | $221,842 | |||
RECOMMENDED SAVINGS* | $37,358 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $12,765 |
#|Description |
Savings Cost |
Status | Electricity Usage | Other Liquid (haz) | Electricity Usage | Other Liquid (haz) | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | gal | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $9,051 Cost: $5,270 |
$9,051 | 64,185 | - | - |
$9,051 64,185 kWh |
- - gal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $3,091 Cost: $3,576 |
$3,091 | 21,981 | - | - |
$3,091 21,981 kWh |
- - gal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $431 Cost: $487 |
$431 | 2,931 | - | - |
$431 2,931 kWh |
- - gal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $623 Cost: $700 |
$623 | 4,396 | - | - |
$623 4,396 kWh |
- - gal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 3.1191 CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS |
Savings: $24,162 Cost: $2,000 |
- | - | $24,162 | 818 |
- - kWh |
$24,162 818 gal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $37,358 Cost: $12,033 |
$13,196 | 93,493 | $24,162 | 818 | $13,196 93,493 kWh |
$24,162 818 gal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $12,765 Cost: $9,546 |
$12,765 | 90,562 | - | - | $12,765 90,562 kWh |
- - gal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | gal | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Other Liquid (haz) | Electricity Usage | Other Liquid (haz) |