Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Iowa State University |
---|---|
Assessment Year | 2001 |
Principal Product | door skins |
NAICS | n/a |
SIC | 2431 - Millwork |
Sales | $10,000,000-$50,000,000 |
# of Employees | 84 |
Plant Area (Sq.Ft.) | 123,500 |
Annual Production | 4,576,000 Pieces |
Production Hrs. Annual | 8,736 |
Location (State) | IA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $528,611 | 22,198,500 | kWh | $0.02 |
Electricity Demand | $293,625 | 42,924 | kW-months/year | $6.84 |
Natural Gas | $261,016 | 52,247 | MMBtu | $5.00 |
TOTAL ENERGY COSTS | $1,133,540 | |||
RECOMMENDED SAVINGS* | $206,314 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $2,944 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (non-haz) | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (non-haz) | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | lb | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $339 Cost: $809 |
$142 | 5,928 | $197 | 29 | - | - | - | - | - | - |
$142 5,928 kWh |
$197 29 kW-months/year |
- - MMBtu |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $95 Cost: $266 |
$95 | 3,971 | - | - | - | - | - | - | - | - |
$95 3,971 kWh |
- - kW-months/year |
- - MMBtu |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $1,344 Cost: $160 |
$967 | 40,449 | $377 | 55 | - | - | - | - | - | - |
$967 40,449 kWh |
$377 55 kW-months/year |
- - MMBtu |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $949 Cost: $120 |
$722 | 30,206 | $227 | 42 | - | - | - | - | - | - |
$722 30,206 kWh |
$227 42 kW-months/year |
- - MMBtu |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $651 Cost: $1,176 |
$(-35) | (-1,466) | $(-25) | (-4) | $711 | 148 | - | - | - | - |
$(-35) (-1,466) kWh |
$(-25) (-4) kW-months/year |
$711 148 MMBtu |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $722 Cost: - |
$517 | 21,611 | $205 | 30 | - | - | - | - | - | - |
$517 21,611 kWh |
$205 30 kW-months/year |
- - MMBtu |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.3132 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS |
Savings: $2,084 Cost: $91 |
- | - | $2,084 | 305 | - | - | - | - | - | - |
- - kWh |
$2,084 305 kW-months/year |
- - MMBtu |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.1213 DIRECT WARMEST AIR TO COMBUSTION INTAKE |
Savings: $27,169 Cost: $14,000 |
- | - | - | - | $27,169 | 5,744 | - | - | - | - |
- - kWh |
- - kW-months/year |
$27,169 5,744 MMBtu |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 4.131 MODIFY PROCESS TO REDUCE MATERIAL USE/COST |
Savings: $114,660 Cost: $46 |
- | - | - | - | - | - | - | - | $114,660 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - lb |
$114,660 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 3.7198 REDUCE / ELIMINATE USE OF DISPOSABLE PRODUCT |
Savings: $58,301 Cost: $3,701 |
- | - | - | - | - | - | $58,301 | 1,053 | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$58,301 1,053 lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $206,314 Cost: $20,369 |
$2,408 | 100,699 | $3,065 | 457 | $27,880 | 5,892 | $58,301 | 1,053 | $114,660 | - | $2,408 100,699 kWh |
$3,065 457 kW-months/year |
$27,880 5,892 MMBtu |
$58,301 1,053 lb |
$114,660 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $2,944 Cost: $1,456 |
$1,654 | 69,189 | $579 | 93 | $711 | 148 | - | - | - | - | $1,654 69,189 kWh |
$579 93 kW-months/year |
$711 148 MMBtu |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | lb | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (non-haz) | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (non-haz) | Ancillary Material Cost |