Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Illinois, Chicago |
---|---|
Assessment Year | 2001 |
Principal Product | Assembly of Drive Axels |
NAICS | n/a |
SIC | 3799 - Transportation Equipment, Nec |
Sales | $50,000,000-$100,000,000 |
# of Employees | 245 |
Plant Area (Sq.Ft.) | 160,590 |
Annual Production | 5,000 Pieces |
Production Hrs. Annual | 5,100 |
Location (State) | IL |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $116,799 | 2,899,462 | kWh | $0.04 |
Electricity Demand | $103,389 | 8,368 | kW-months/year | $12.36 |
Electricity Fees | $24,737 | - | $ | - |
Natural Gas | $38,919 | 7,463 | MMBtu | $5.21 |
TOTAL ENERGY COSTS | $312,836 | |||
RECOMMENDED SAVINGS* | $630,248 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $33,796 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Solid Waste (non-haz) | Personnel Changes | Administrative Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Solid Waste (non-haz) | Personnel Changes | Administrative Changes | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | $ | MMBtu | $ | lb | $ | $ | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $1,962 Cost: $1,500 |
$1,148 | 27,989 | $814 | 66 | - | - | - | - | - | - | - | - | - | - | - | - |
$1,148 27,989 kWh |
$814 66 kW-months/year |
- - $ |
- - MMBtu |
- - lb |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $26,503 Cost: $92,040 |
$15,527 | 378,706 | $10,976 | 888 | - | - | - | - | - | - | - | - | - | - | - | - |
$15,527 378,706 kWh |
$10,976 888 kW-months/year |
- - $ |
- - MMBtu |
- - lb |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $522 Cost: $1,677 |
$110 | 2,681 | $45 | 4 | - | - | - | - | - | - | $248 | - | - | - | $119 | - |
$110 2,681 kWh |
$45 4 kW-months/year |
- - $ |
- - MMBtu |
- - lb |
$248 - $ |
- - $ |
$119 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $1,569 Cost: $7,461 |
$903 | 22,020 | $640 | 52 | - | - | - | - | - | - | $26 | - | - | - | - | - |
$903 22,020 kWh |
$640 52 kW-months/year |
- - $ |
- - MMBtu |
- - lb |
$26 - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $1,359 Cost: $2,516 |
$1,196 | 29,163 | $163 | 13 | - | - | - | - | - | - | - | - | - | - | - | - |
$1,196 29,163 kWh |
$163 13 kW-months/year |
- - $ |
- - MMBtu |
- - lb |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $369 Cost: $1,551 |
$138 | 3,367 | $231 | 19 | - | - | - | - | - | - | - | - | - | - | - | - |
$138 3,367 kWh |
$231 19 kW-months/year |
- - $ |
- - MMBtu |
- - lb |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $222 Cost: $832 |
- | - | - | - | - | - | $222 | 43 | - | - | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
- - $ |
$222 43 MMBtu |
- - lb |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $652 Cost: $2,670 |
- | - | - | - | - | - | $652 | 125 | - | - | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
- - $ |
$652 125 MMBtu |
- - lb |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $128 Cost: $370 |
- | - | - | - | - | - | $128 | 25 | - | - | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
- - $ |
$128 25 MMBtu |
- - lb |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 2.3132 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS |
Savings: $162 Cost: - |
- | - | - | - | $162 | - | - | - | - | - | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$162 - $ |
- - MMBtu |
- - lb |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
11: 3.5316 CONTRACT A WOOD PALLET RECYCLING COMPANY |
Savings: $28,000 Cost: $5,300 |
- | - | - | - | - | - | - | - | $28,000 | - | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
$28,000 - lb |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
12: 4.447 AUTOMATE PAYROLL SYSTEM |
Savings: $84,800 Cost: $6,670 |
- | - | - | - | - | - | - | - | - | - | $69,800 | - | $15,000 | - | - | - |
- - kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
- - lb |
$69,800 - $ |
$15,000 - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
13: 4.426 MODIFY WORKLOAD |
Savings: $484,000 Cost: $66,100 |
- | - | - | - | - | - | - | - | - | - | $480,000 | - | $4,000 | - | - | - |
- - kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
- - lb |
$480,000 - $ |
$4,000 - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $630,248 Cost: $188,687 |
$19,022 | 463,926 | $12,869 | 1,042 | $162 | - | $1,002 | 193 | $28,000 | - | $550,074 | - | $19,000 | - | $119 | - | $19,022 463,926 kWh |
$12,869 1,042 kW-months/year |
$162 - $ |
$1,002 193 MMBtu |
$28,000 - lb |
$550,074 - $ |
$19,000 - $ |
$119 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $33,796 Cost: $19,286 |
$3,357 | 81,853 | $1,662 | 135 | $162 | - | $222 | 43 | $28,000 | - | $274 | - | - | - | $119 | - | $3,357 81,853 kWh |
$1,662 135 kW-months/year |
$162 - $ |
$222 43 MMBtu |
$28,000 - lb |
$274 - $ |
- - $ |
$119 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | $ | MMBtu | $ | lb | $ | $ | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Solid Waste (non-haz) | Personnel Changes | Administrative Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Solid Waste (non-haz) | Personnel Changes | Administrative Changes | Ancillary Material Cost |