IAC Assessment: IC0024
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: IC0024
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Illinois, Chicago
Assessment Year 2001
Principal Product Brass and Ferrous Castings
NAICS n/a
SIC 3366 - Copper Foundries
Sales $10,000,000-$50,000,000
# of Employees 149
Plant Area (Sq.Ft.) 87,100
Annual Production 3,500,000 Pounds
Production Hrs. Annual 6,120
Location (State) IL
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $271,804 8,377,352 kWh $0.03
Electricity Demand $224,747 17,014 kW-months/year $13.21
Electricity Fees $58,001 - $ -
Natural Gas $62,174 6,724 MMBtu $9.25
TOTAL ENERGY COSTS $663,676
RECOMMENDED SAVINGS* $1,232,435 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $392,179
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas Solid Waste (non-haz) Personnel Changes Administrative Changes Primary Raw Material Ancillary Material Cost Electricity Usage Electricity Demand Natural Gas Solid Waste (non-haz) Personnel Changes Administrative Changes Primary Raw Material Ancillary Material Cost
$ kWh $ kW-months/year $ MMBtu $ lb $ $ $ $ $ $ $ $
01: 2.1117 RELOCATE OVEN / FURNACE TO MORE EFFICIENT LOCATION Savings:
$27,240
Cost:
$6,825
$17,250 492,800 $9,990 756 - - - - - - - - - - - - $17,250
492,800
kWh
$9,990
756
kW-months/year
-
-
MMBtu
-
-
lb
-
-
$
-
-
$
-
-
$
-
-
$
02: 2.3191 USE DEMAND CONTROLLER OR LOAD SHEDDER Savings:
$11,240
Cost:
$3,280
- - $11,240 1,702 - - - - - - - - - - - - -
-
kWh
$11,240
1,702
kW-months/year
-
-
MMBtu
-
-
lb
-
-
$
-
-
$
-
-
$
-
-
$
03: 2.1121 USE INSULATION IN FURNACES TO FACILITATE HEATING / COOLING Savings:
$7,403
Cost:
$2,000
$7,403 56,136 - - - - - - - - - - - - - - $7,403
56,136
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
lb
-
-
$
-
-
$
-
-
$
-
-
$
04: 2.1121 USE INSULATION IN FURNACES TO FACILITATE HEATING / COOLING Savings:
$1,943
Cost:
$4,000
$1,943 55,503 - - - - - - - - - - - - - - $1,943
55,503
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
lb
-
-
$
-
-
$
-
-
$
-
-
$
05: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$13,634
Cost:
$4,300
$8,156 233,037 $5,478 415 - - - - - - - - - - - - $8,156
233,037
kWh
$5,478
415
kW-months/year
-
-
MMBtu
-
-
lb
-
-
$
-
-
$
-
-
$
-
-
$
06: 2.4321 UPGRADE OBSOLETE EQUIPMENT Savings:
$9,500
Cost:
$16,800
$5,670 162,000 $3,830 290 - - - - - - - - - - - - $5,670
162,000
kWh
$3,830
290
kW-months/year
-
-
MMBtu
-
-
lb
-
-
$
-
-
$
-
-
$
-
-
$
07: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$9,642
Cost:
$32,917
$5,079 145,119 $3,804 288 - - - - $1,192 - - - - - $(-433) - $5,079
145,119
kWh
$3,804
288
kW-months/year
-
-
MMBtu
-
-
lb
$1,192
-
$
-
-
$
-
-
$
$(-433)
-
$
08: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$1,811
Cost:
$7,956
$682 19,476 $1,101 83 - - - - $29 - - - - - $(-1) - $682
19,476
kWh
$1,101
83
kW-months/year
-
-
MMBtu
-
-
lb
$29
-
$
-
-
$
-
-
$
$(-1)
-
$
09: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$1,134
Cost:
$945
$210 5,992 $106 8 - - - - $674 - - - - - $144 - $210
5,992
kWh
$106
8
kW-months/year
-
-
MMBtu
-
-
lb
$674
-
$
-
-
$
-
-
$
$144
-
$
10: 2.6232 INSTALL SET-BACK TIMERS Savings:
$4,823
Cost:
$968
- - - - $4,823 522 - - - - - - - - - - -
-
kWh
-
-
kW-months/year
$4,823
522
MMBtu
-
-
lb
-
-
$
-
-
$
-
-
$
-
-
$
11: 2.6232 INSTALL SET-BACK TIMERS Savings:
$2,245
Cost:
$1,741
- - - - $2,245 243 - - - - - - - - - - -
-
kWh
-
-
kW-months/year
$2,245
243
MMBtu
-
-
lb
-
-
$
-
-
$
-
-
$
-
-
$
12: 3.5221 RECYCLE CASTING SAND Savings:
$765,000
Cost:
-
- - - - - - $790,000 - - - - - $(-25,000) - - - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
$790,000
-
lb
-
-
$
-
-
$
$(-25,000)
-
$
-
-
$
13: 4.5210 CLEAR AND RENT EXISTING SPACE Savings:
$365,820
Cost:
$3,920
- - - - - - - - - - $365,820 - - - - - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
lb
-
-
$
$365,820
-
$
-
-
$
-
-
$
14: 4.4230 MOVE PRODUCT USING MECHANICAL MEANS Savings:
$11,000
Cost:
$7,000
- - - - - - - - $11,000 - - - - - - - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
lb
$11,000
-
$
-
-
$
-
-
$
-
-
$
TOTAL RECOMMENDED Savings:
$1,232,435
Cost:
$92,652
$46,393 1,170,063 $35,549 3,542 $7,068 765 $790,000 - $12,895 - $365,820 - $(-25,000) - $(-290) - $46,393
1,170,063
kWh
$35,549
3,542
kW-months/year
$7,068
765
MMBtu
$790,000
-
lb
$12,895
-
$
$365,820
-
$
$(-25,000)
-
$
$(-290)
-
$
TOTAL IMPLEMENTED Savings:
$392,179
Cost:
$16,906
$17,712 350,668 $5,584 423 $2,245 243 - - $674 - $365,820 - - - $144 - $17,712
350,668
kWh
$5,584
423
kW-months/year
$2,245
243
MMBtu
-
-
lb
$674
-
$
$365,820
-
$
-
-
$
$144
-
$
Savings
Cost
$ kWh $ kW-months/year $ MMBtu $ lb $ $ $ $ $ $ $ $
Electricity Usage Electricity Demand Natural Gas Solid Waste (non-haz) Personnel Changes Administrative Changes Primary Raw Material Ancillary Material Cost Electricity Usage Electricity Demand Natural Gas Solid Waste (non-haz) Personnel Changes Administrative Changes Primary Raw Material Ancillary Material Cost