Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Illinois, Chicago |
---|---|
Assessment Year | 2004 |
Principal Product | Courrugate |
NAICS | 322211 - Corrugated and Solid Fiber Box Manufacturing |
SIC | 2653 - Corrugated And Solid Fiber Boxes |
Sales | $10,000,000-$50,000,000 |
# of Employees | 105 |
Plant Area (Sq.Ft.) | 200,540 |
Annual Production | 564,000 Thousand Feet |
Production Hrs. Annual | 6,120 |
Location (State) | KS |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $172,548 | 3,664,500 | kWh | $0.05 |
Electricity Demand | $40,445 | 7,775 | kW-months/year | $5.20 |
Electricity Fees | $38,193 | - | $ | - |
Natural Gas | $228,671 | 32,710 | MMBtu | $6.99 |
TOTAL ENERGY COSTS | $479,857 | |||
RECOMMENDED SAVINGS* | $101,891 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Water Disposal | Personnel Changes | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Water Disposal | Personnel Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | $ | MMBtu | $ | Tgal | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.2124 INSTALL DE-AERATOR IN PLACE OF CONDENSATE TANK |
Savings: $41,155 Cost: $96,800 |
- | - | - | - | - | - | $36,565 | 5,231 | $4,590 | 410,681 | - | - |
- - kWh |
- - kW-months/year |
- - $ |
$36,565 5,231 MMBtu |
$4,590 410,681 Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.2136 INSTALL / REPAIR INSULATION ON STEAM LINES |
Savings: $1,540 Cost: $2,212 |
- | - | - | - | - | - | $1,540 | 220 | - | - | - | - |
- - kWh |
- - kW-months/year |
- - $ |
$1,540 220 MMBtu |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7241 INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT |
Savings: $9,520 Cost: $33,750 |
- | - | - | - | - | - | $9,520 | 1,362 | - | - | - | - |
- - kWh |
- - kW-months/year |
- - $ |
$9,520 1,362 MMBtu |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7221 LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA |
Savings: $1,992 Cost: - |
- | - | - | - | - | - | $1,992 | 285 | - | - | - | - |
- - kWh |
- - kW-months/year |
- - $ |
$1,992 285 MMBtu |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.2135 REPAIR AND ELIMINATE STEAM LEAKS |
Savings: $7,304 Cost: $900 |
- | - | - | - | - | - | $7,304 | 1,045 | - | - | - | - |
- - kWh |
- - kW-months/year |
- - $ |
$7,304 1,045 MMBtu |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.6126 KEEP SOLID FUELS / RAW MATERIALS DRY |
Savings: $1,999 Cost: $11,950 |
- | - | - | - | - | - | $1,999 | 286 | - | - | - | - |
- - kWh |
- - kW-months/year |
- - $ |
$1,999 286 MMBtu |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $1,790 Cost: $1,700 |
$1,466 | 27,114 | $257 | 49 | $67 | - | - | - | - | - | - | - |
$1,466 27,114 kWh |
$257 49 kW-months/year |
$67 - $ |
- - MMBtu |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.4322 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES |
Savings: $222 Cost: $75 |
$213 | 3,947 | - | - | $9 | - | - | - | - | - | - | - |
$213 3,947 kWh |
- - kW-months/year |
$9 - $ |
- - MMBtu |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $29,026 Cost: $142,221 |
$30,640 | 567,369 | $6,045 | 1,162 | $1,369 | - | - | - | - | - | $(-9,028) | - |
$30,640 567,369 kWh |
$6,045 1,162 kW-months/year |
$1,369 - $ |
- - MMBtu |
- - Tgal |
$(-9,028) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $689 Cost: $1,252 |
$146 | 2,698 | $19 | 4 | $6 | - | - | - | - | - | $518 | - |
$146 2,698 kWh |
$19 4 kW-months/year |
$6 - $ |
- - MMBtu |
- - Tgal |
$518 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
11: 2.6126 KEEP SOLID FUELS / RAW MATERIALS DRY |
Savings: $819 Cost: $920 |
$784 | 14,516 | - | - | $35 | - | - | - | - | - | - | - |
$784 14,516 kWh |
- - kW-months/year |
$35 - $ |
- - MMBtu |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
12: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $1,626 Cost: $955 |
$1,284 | 23,770 | $285 | 55 | $57 | - | - | - | - | - | - | - |
$1,284 23,770 kWh |
$285 55 kW-months/year |
$57 - $ |
- - MMBtu |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
13: 2.6126 KEEP SOLID FUELS / RAW MATERIALS DRY |
Savings: $260 Cost: - |
$88 | 1,723 | $168 | 32 | $4 | - | - | - | - | - | - | - |
$88 1,723 kWh |
$168 32 kW-months/year |
$4 - $ |
- - MMBtu |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
14: 2.6126 KEEP SOLID FUELS / RAW MATERIALS DRY |
Savings: $3,949 Cost: $750 |
$1,124 | 20,808 | - | - | $106 | - | $2,719 | 389 | - | - | - | - |
$1,124 20,808 kWh |
- - kW-months/year |
$106 - $ |
$2,719 389 MMBtu |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $101,891 Cost: $293,485 |
$35,745 | 661,945 | $6,774 | 1,302 | $1,653 | - | $61,639 | 8,818 | $4,590 | 410,681 | $(-8,510) | - | $35,745 661,945 kWh |
$6,774 1,302 kW-months/year |
$1,653 - $ |
$61,639 8,818 MMBtu |
$4,590 410,681 Tgal |
$(-8,510) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | $ | MMBtu | $ | Tgal | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Water Disposal | Personnel Changes | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Water Disposal | Personnel Changes |