IAC Assessment: LL0102
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: LL0102
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Louisiana, Lafayette
Assessment Year 2001
Principal Product Pipe Spacers and Insulators
NAICS n/a
SIC 3599 - Industrial Machinery, Nec
Sales $1,000,000-$5,000,000
# of Employees 45
Plant Area (Sq.Ft.) 37,500
Annual Production 14 Pieces
Production Hrs. Annual 2,080
Location (State) LA
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $9,691 223,916 kWh $0.04
Electricity Demand $5,665 1,008 kW-months/year $5.62
Electricity Fees $1,129 - $ -
Natural Gas $7,041 800 MMBtu $8.80
TOTAL ENERGY COSTS $24,875
RECOMMENDED SAVINGS* $5,078 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $4,406
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Electricity Fees Solid Waste (non-haz) Electricity Usage Electricity Demand Electricity Fees Solid Waste (non-haz)
$ kWh $ kW-months/year $ $ $ lb
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$672
Cost:
$2,135
$388 9,132 $258 46 $26 - - - $388
9,132
kWh
$258
46
kW-months/year
$26
-
$
-
-
lb
02: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$655
Cost:
$3,697
$630 14,812 - - $25 - - - $630
14,812
kWh
-
-
kW-months/year
$25
-
$
-
-
lb
03: 2.3212 OPTIMIZE PLANT POWER FACTOR Savings:
$1,262
Cost:
$1,200
- - $1,262 19 - - - - -
-
kWh
$1,262
19
kW-months/year
-
-
$
-
-
lb
04: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$1,140
Cost:
$2,890
$712 16,737 $384 68 $44 - - - $712
16,737
kWh
$384
68
kW-months/year
$44
-
$
-
-
lb
05: 3.1192 REDUCE SCRAP PRODUCTION Savings:
$1,349
Cost:
-
- - - - - - $1,349 6,240 -
-
kWh
-
-
kW-months/year
-
-
$
$1,349
6,240
lb
TOTAL RECOMMENDED Savings:
$5,078
Cost:
$9,922
$1,730 40,681 $1,904 133 $95 - $1,349 6,240 $1,730
40,681
kWh
$1,904
133
kW-months/year
$95
-
$
$1,349
6,240
lb
TOTAL IMPLEMENTED Savings:
$4,406
Cost:
$7,787
$1,342 31,549 $1,646 87 $69 - $1,349 6,240 $1,342
31,549
kWh
$1,646
87
kW-months/year
$69
-
$
$1,349
6,240
lb
Savings
Cost
$ kWh $ kW-months/year $ $ $ lb
Electricity Usage Electricity Demand Electricity Fees Solid Waste (non-haz) Electricity Usage Electricity Demand Electricity Fees Solid Waste (non-haz)