Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Loyola Marymount University |
---|---|
Assessment Year | 2001 |
Principal Product | fiberglass |
NAICS | n/a |
SIC | 3714 - Motor Vehicle Parts And Accessories |
Sales | $10,000,000-$50,000,000 |
# of Employees | 200 |
Plant Area (Sq.Ft.) | 113,668 |
Annual Production | 50,000 Pieces |
Production Hrs. Annual | 2,520 |
Location (State) | CA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $100,936 | 1,312,400 | kWh | $0.08 |
Electricity Demand | $67,227 | 10,485 | kW-months/year | $6.41 |
Electricity Fees | $24,001 | - | $ | - |
Natural Gas | $60,280 | 6,913 | MMBtu | $8.72 |
TOTAL ENERGY COSTS | $252,444 | |||
RECOMMENDED SAVINGS* | $128,787 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $124,403 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Personnel Changes | Administrative Changes | Electricity Usage | Electricity Demand | Personnel Changes | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $21,040 Cost: $1,050 |
$16,420 | 124,816 | $5,400 | 616 | $(-780) | - | - | - |
$16,420 124,816 kWh |
$5,400 616 kW-months/year |
$(-780) - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $1,817 Cost: - |
$1,055 | 8,016 | $762 | 86 | - | - | - | - |
$1,055 8,016 kWh |
$762 86 kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7145 INSTALL SKYLIGHTS |
Savings: $3,232 Cost: $4,900 |
$2,352 | 17,876 | $880 | 101 | - | - | - | - |
$2,352 17,876 kWh |
$880 101 kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7144 INSTALL SPECTRAL REFLECTORS / DELAMP |
Savings: $1,152 Cost: $1,165 |
$971 | 7,384 | $181 | 20 | - | - | - | - |
$971 7,384 kWh |
$181 20 kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.3131 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS |
Savings: $21,776 Cost: $300 |
- | - | - | - | - | - | $21,776 | - |
- - kWh |
- - kW-months/year |
- - $ |
$21,776 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 4.121 MAINTAIN CLEAN CONDITIONS BEFORE PAINTING |
Savings: $19,656 Cost: $319 |
- | - | - | - | $19,656 | - | - | - |
- - kWh |
- - kW-months/year |
$19,656 - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 4.426 MODIFY WORKLOAD |
Savings: $43,680 Cost: $5,000 |
- | - | - | - | $43,680 | - | - | - |
- - kWh |
- - kW-months/year |
$43,680 - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 4.431 TRAIN OPERATORS FOR MAXIMUM OPERATING EFFICIENCY |
Savings: $16,434 Cost: - |
- | - | - | - | $16,434 | - | - | - |
- - kWh |
- - kW-months/year |
$16,434 - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $128,787 Cost: $12,734 |
$20,798 | 158,092 | $7,223 | 823 | $78,990 | - | $21,776 | - | $20,798 158,092 kWh |
$7,223 823 kW-months/year |
$78,990 - $ |
$21,776 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $124,403 Cost: $6,669 |
$17,475 | 132,832 | $6,162 | 702 | $78,990 | - | $21,776 | - | $17,475 132,832 kWh |
$6,162 702 kW-months/year |
$78,990 - $ |
$21,776 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Personnel Changes | Administrative Changes | Electricity Usage | Electricity Demand | Personnel Changes | Administrative Changes |