Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Loyola Marymount University |
---|---|
Assessment Year | 2001 |
Principal Product | double diaphragm pumps |
NAICS | n/a |
SIC | 3561 - Pumps And Pumping Equipment |
Sales | $50,000,000-$100,000,000 |
# of Employees | 235 |
Plant Area (Sq.Ft.) | 157,216 |
Annual Production | 84,000 Pieces |
Production Hrs. Annual | 5,161 |
Location (State) | CA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $316,872 | 6,688,566 | kWh | $0.05 |
Electricity Demand | $150,301 | 34,456 | kW-months/year | $4.36 |
Electricity Fees | $24,374 | - | $ | - |
Natural Gas | $12,377 | 1,484 | MMBtu | $8.34 |
TOTAL ENERGY COSTS | $503,924 | |||
RECOMMENDED SAVINGS* | $487,476 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $142,830 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Personnel Changes | Administrative Changes | Electricity Usage | Electricity Demand | Personnel Changes | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $10,371 Cost: $19,200 |
$8,501 | 85,466 | $1,870 | 199 | - | - | - | - |
$8,501 85,466 kWh |
$1,870 199 kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7121 UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT |
Savings: $5,951 Cost: $550 |
$5,004 | 36,757 | $947 | 89 | - | - | - | - |
$5,004 36,757 kWh |
$947 89 kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $6,264 Cost: $800 |
$4,960 | 44,126 | $1,304 | 108 | - | - | - | - |
$4,960 44,126 kWh |
$1,304 108 kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $5,982 Cost: - |
$4,904 | 49,298 | $1,078 | 115 | - | - | - | - |
$4,904 49,298 kWh |
$1,078 115 kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $30,965 Cost: $12,950 |
$24,506 | 217,908 | $6,459 | 504 | - | - | - | - |
$24,506 217,908 kWh |
$6,459 504 kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.3131 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS |
Savings: $100,699 Cost: $450 |
- | - | - | - | - | - | $100,699 | - |
- - kWh |
- - kW-months/year |
- - $ |
$100,699 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 3.6193 INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS |
Savings: $8,944 Cost: $11,800 |
- | - | - | - | - | - | $8,944 | - |
- - kWh |
- - kW-months/year |
- - $ |
$8,944 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 4.311 SCHEDULE DELIVERIES ACCORDING TO DEMAND |
Savings: $207,000 Cost: $1,000 |
- | - | - | - | - | - | $207,000 | - |
- - kWh |
- - kW-months/year |
- - $ |
$207,000 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 4.612 CONTRACT OUT MAINTENANCE |
Savings: $7,300 Cost: - |
- | - | - | - | $7,300 | - | - | - |
- - kWh |
- - kW-months/year |
$7,300 - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 4.131 MODIFY PROCESS TO REDUCE MATERIAL USE/COST |
Savings: $104,000 Cost: $24,000 |
- | - | - | - | $104,000 | - | - | - |
- - kWh |
- - kW-months/year |
$104,000 - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $487,476 Cost: $70,750 |
$47,875 | 433,555 | $11,658 | 1,015 | $111,300 | - | $316,643 | - | $47,875 433,555 kWh |
$11,658 1,015 kW-months/year |
$111,300 - $ |
$316,643 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $142,830 Cost: $56,350 |
$18,465 | 166,349 | $4,121 | 396 | $111,300 | - | $8,944 | - | $18,465 166,349 kWh |
$4,121 396 kW-months/year |
$111,300 - $ |
$8,944 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Personnel Changes | Administrative Changes | Electricity Usage | Electricity Demand | Personnel Changes | Administrative Changes |