Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Loyola Marymount University |
---|---|
Assessment Year | 2003 |
Principal Product | asphalt composite roofing shingles |
NAICS | 324122 - Asphalt Shingle and Coating Materials Manufacturing |
SIC | 2952 - Asphalt Felts And Coatings |
Sales | $10,000,000-$50,000,000 |
# of Employees | 100 |
Plant Area (Sq.Ft.) | 125,000 |
Annual Production | 132,000,000 Pieces |
Production Hrs. Annual | 7,440 |
Location (State) | CA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $679,366 | 6,269,238 | kWh | $0.11 |
Electricity Demand | $171,979 | 12,996 | kW-months/year | $13.23 |
Electricity Fees | $49,690 | - | $ | - |
Natural Gas | $1,581,309 | 184,310 | MMBtu | $8.58 |
TOTAL ENERGY COSTS | $2,510,344 | |||
RECOMMENDED SAVINGS* | $953,119 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $843,354 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Water Disposal | Personnel Changes | Administrative Changes | Primary Product | Increase in Production | Electricity Usage | Electricity Demand | Water Disposal | Personnel Changes | Administrative Changes | Primary Product | Increase in Production | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | Tgal | $ | $ | $ | $ | $ | $ | $ | % | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7124 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED |
Savings: $3,065 Cost: - |
$2,553 | 22,570 | $512 | 36 | - | - | - | - | - | - | - | - | - | - |
$2,553 22,570 kWh |
$512 36 kW-months/year |
- - Tgal |
- - $ |
- - $ |
- - $ |
- - % |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $7,111 Cost: $4,650 |
$6,743 | 49,945 | $368 | 109 | - | - | - | - | - | - | - | - | - | - |
$6,743 49,945 kWh |
$368 109 kW-months/year |
- - Tgal |
- - $ |
- - $ |
- - $ |
- - % |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $1,650 Cost: $951 |
$1,374 | 12,150 | $276 | 20 | - | - | - | - | - | - | - | - | - | - |
$1,374 12,150 kWh |
$276 20 kW-months/year |
- - Tgal |
- - $ |
- - $ |
- - $ |
- - % |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4131 SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY |
Savings: $2,317 Cost: $3,200 |
$1,930 | 17,063 | $387 | 28 | - | - | - | - | - | - | - | - | - | - |
$1,930 17,063 kWh |
$387 28 kW-months/year |
- - Tgal |
- - $ |
- - $ |
- - $ |
- - % |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 3.4115 RECOVER AND REUSE COOLING WATER |
Savings: $16,200 Cost: $1,000 |
- | - | - | - | $16,200 | 4,712,000 | - | - | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$16,200 4,712,000 Tgal |
- - $ |
- - $ |
- - $ |
- - % |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 4.625 DEVELOP STANDARD OPERATING PROCEDURES |
Savings: $36,400 Cost: $14,567 |
- | - | - | - | - | - | - | - | - | - | - | - | $36,400 | - |
- - kWh |
- - kW-months/year |
- - Tgal |
- - $ |
- - $ |
- - $ |
$36,400 - % |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 4.625 DEVELOP STANDARD OPERATING PROCEDURES |
Savings: $25,093 Cost: $15,842 |
- | - | - | - | - | - | - | - | - | - | $25,093 | - | - | - |
- - kWh |
- - kW-months/year |
- - Tgal |
- - $ |
- - $ |
$25,093 - $ |
- - % |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 4.611 BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE |
Savings: $105,000 Cost: $40,872 |
- | - | - | - | - | - | $105,000 | - | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
- - Tgal |
$105,000 - $ |
- - $ |
- - $ |
- - % |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 4.111 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK |
Savings: $672,000 Cost: $100,000 |
- | - | - | - | - | - | - | - | - | - | - | - | $672,000 | - |
- - kWh |
- - kW-months/year |
- - Tgal |
- - $ |
- - $ |
- - $ |
$672,000 - % |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 4.514 RE-ARRANGE EQUIPMENT LAYOUT TO REDUCE HANDLING COSTS |
Savings: $82,232 Cost: $25,000 |
- | - | - | - | - | - | $82,232 | - | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
- - Tgal |
$82,232 - $ |
- - $ |
- - $ |
- - % |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
11: 4.132 PURCHASE NEW EQUIPMENT TO REDUCE MATERIAL USE / COST |
Savings: $1,700 Cost: $2,300 |
- | - | - | - | - | - | - | - | $1,700 | - | - | - | - | - |
- - kWh |
- - kW-months/year |
- - Tgal |
- - $ |
$1,700 - $ |
- - $ |
- - % |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
12: 2.8114 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE |
Savings: $351 Cost: - |
- | - | - | - | - | - | - | - | $351 | - | - | - | - | - |
- - kWh |
- - kW-months/year |
- - Tgal |
- - $ |
$351 - $ |
- - $ |
- - % |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $953,119 Cost: $208,382 |
$12,600 | 101,728 | $1,543 | 193 | $16,200 | 4,712,000 | $187,232 | - | $2,051 | - | $25,093 | - | $708,400 | - | $12,600 101,728 kWh |
$1,543 193 kW-months/year |
$16,200 4,712,000 Tgal |
$187,232 - $ |
$2,051 - $ |
$25,093 - $ |
$708,400 - % |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $843,354 Cost: $165,210 |
$10,047 | 79,158 | $1,031 | 157 | $16,200 | 4,712,000 | $82,232 | - | $351 | - | $25,093 | - | $708,400 | - | $10,047 79,158 kWh |
$1,031 157 kW-months/year |
$16,200 4,712,000 Tgal |
$82,232 - $ |
$351 - $ |
$25,093 - $ |
$708,400 - % |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | Tgal | $ | $ | $ | $ | $ | $ | $ | % | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Water Disposal | Personnel Changes | Administrative Changes | Primary Product | Increase in Production | Electricity Usage | Electricity Demand | Water Disposal | Personnel Changes | Administrative Changes | Primary Product | Increase in Production |