IAC Assessment: LM0096
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: LM0096
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Loyola Marymount University
Assessment Year 2005
Principal Product capacitors
NAICS 334416 - Capacitor, Resistor, Coil, Transformer, and Other Inductor Manufacturing
SIC 3675 - Electronic Capacitors
Sales $10,000,000-$50,000,000
# of Employees 400
Plant Area (Sq.Ft.) 111,250
Annual Production 50,000 Pounds
Production Hrs. Annual 4,000
Location (State) CA
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $474,717 9,216,640 kWh $0.05
Electricity Demand $275,196 18,859 kW-months/year $14.59
Electricity Fees $98,660 - $ -
TOTAL ENERGY COSTS $848,573
RECOMMENDED SAVINGS* $561,184 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $15,931
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Personnel Changes Electricity Usage Electricity Demand Personnel Changes
$ kWh $ kW-months/year $ $
01: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$6,099
Cost:
$1,300
$5,363 49,122 $736 73 - - $5,363
49,122
kWh
$736
73
kW-months/year
-
-
$
02: 2.4224 UPGRADE CONTROLS ON COMPRESSORS Savings:
$5,434
Cost:
$350
$5,434 104,900 - - - - $5,434
104,900
kWh
-
-
kW-months/year
-
-
$
03: 2.7233 USE PROPERLY DESIGNED AND SIZED HVAC EQUIPMENT Savings:
$91,510
Cost:
$125,000
$41,270 796,700 $50,240 3,420 - - $41,270
796,700
kWh
$50,240
3,420
kW-months/year
-
-
$
04: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS Savings:
$364
Cost:
$400
$247 3,764 $117 11 - - $247
3,764
kWh
$117
11
kW-months/year
-
-
$
05: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS Savings:
$493
Cost:
$532
$271 5,226 $222 16 - - $271
5,226
kWh
$222
16
kW-months/year
-
-
$
06: 2.7124 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED Savings:
$4,034
Cost:
$90
$2,108 40,700 $1,926 131 - - $2,108
40,700
kWh
$1,926
131
kW-months/year
-
-
$
07: 4.431 TRAIN OPERATORS FOR MAXIMUM OPERATING EFFICIENCY Savings:
$262,500
Cost:
$71,250
- - - - $262,500 - -
-
kWh
-
-
kW-months/year
$262,500
-
$
08: 4.625 DEVELOP STANDARD OPERATING PROCEDURES Savings:
$140,625
Cost:
$10,800
- - - - $140,625 - -
-
kWh
-
-
kW-months/year
$140,625
-
$
09: 4.611 BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE Savings:
$46,875
Cost:
$2,000
- - - - $46,875 - -
-
kWh
-
-
kW-months/year
$46,875
-
$
10: 4.431 TRAIN OPERATORS FOR MAXIMUM OPERATING EFFICIENCY Savings:
$3,250
Cost:
$1,125
- - - - $3,250 - -
-
kWh
-
-
kW-months/year
$3,250
-
$
TOTAL RECOMMENDED Savings:
$561,184
Cost:
$212,847
$54,693 1,000,412 $53,241 3,651 $453,250 - $54,693
1,000,412
kWh
$53,241
3,651
kW-months/year
$453,250
-
$
TOTAL IMPLEMENTED Savings:
$15,931
Cost:
$2,140
$13,152 198,486 $2,779 215 - - $13,152
198,486
kWh
$2,779
215
kW-months/year
-
-
$
Savings
Cost
$ kWh $ kW-months/year $ $
Electricity Usage Electricity Demand Personnel Changes Electricity Usage Electricity Demand Personnel Changes