Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Massachusetts |
---|---|
Assessment Year | 1988 |
Principal Product | PULP & PAPER MACHINERY |
NAICS | n/a |
SIC | 3554 - Paper Industries Machinery |
Sales | $1,000,000-$5,000,000 |
# of Employees | 56 |
Plant Area (Sq.Ft.) | 0 |
Annual Production | 2,600,000 Pounds |
Production Hrs. Annual | 4,000 |
Location (State) | MA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $152,891 | 1,690,211 | kWh | $0.09 |
LPG | $41,083 | 8,766 | MMBtu | $4.69 |
Fuel Oil #2 | $1,939 | 287 | MMBtu | $6.76 |
TOTAL ENERGY COSTS | $195,913 | |||
RECOMMENDED SAVINGS* | $103,591 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $34,076 |
#|Description |
Savings Cost |
Status | Electricity Usage | LPG | Administrative Changes | Electricity Usage | LPG | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $2,588 Cost: $3,792 |
$2,012 | 24,033 | - | - | $576 | - |
$2,012 24,033 kWh |
- - MMBtu |
$576 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.2491 USE COOLING AIR WHICH COOLS HOT WORK PIECES FOR SPACE HEATING |
Savings: $1,579 Cost: - |
- | - | $1,579 | 375 | - | - |
- - kWh |
$1,579 375 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $311 Cost: $78 |
$311 | 3,810 | - | - | - | - |
$311 3,810 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $609 Cost: - |
$609 | 7,327 | - | - | - | - |
$609 7,327 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $722 Cost: $2,700 |
$722 | 8,499 | - | - | - | - |
$722 8,499 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7494 INSTALL STORM WINDOWS AND DOORS |
Savings: $1,177 Cost: $2,400 |
- | - | $1,177 | 251 | - | - |
- - kWh |
$1,177 251 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.3192 USE FOSSIL FUEL POWERED GENERATOR DURING PEAK DEMAND PERIODS |
Savings: $66,605 Cost: - |
$60,442 | 363,130 | $6,163 | 1,314 | - | - |
$60,442 363,130 kWh |
$6,163 1,314 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.3191 USE DEMAND CONTROLLER OR LOAD SHEDDER |
Savings: $30,000 Cost: $940 |
$30,000 | - | - | - | - | - |
$30,000 - kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $103,591 Cost: $9,910 |
$94,096 | 406,799 | $8,919 | 1,940 | $576 | - | $94,096 406,799 kWh |
$8,919 1,940 MMBtu |
$576 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $34,076 Cost: $7,210 |
$32,323 | 27,843 | $1,177 | 251 | $576 | - | $32,323 27,843 kWh |
$1,177 251 MMBtu |
$576 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | LPG | Administrative Changes | Electricity Usage | LPG | Administrative Changes |