Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Massachusetts |
---|---|
Assessment Year | 2002 |
Principal Product | Electronic Components and Assemblies |
NAICS | n/a |
SIC | 3679 - Electronic Components, Nec |
Sales | $10,000,000-$50,000,000 |
# of Employees | 215 |
Plant Area (Sq.Ft.) | 150,000 |
Annual Production | 50,000 Pounds |
Production Hrs. Annual | 4,992 |
Location (State) | MA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $268,370 | 4,767,840 | kWh | $0.06 |
Electricity Demand | $117,391 | 9,753 | kW-months/year | $12.04 |
Electricity Fees | $35,124 | - | $ | - |
Natural Gas | $74,207 | 8,486 | MMBtu | $8.74 |
TOTAL ENERGY COSTS | $495,887 | |||
RECOMMENDED SAVINGS* | $93,109 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $71,328 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Administrative Changes | Ancillary Material Cost | One-time Revenue or Avoided Cost | Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Administrative Changes | Ancillary Material Cost | One-time Revenue or Avoided Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | Tgal | $ | $ | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 4.212 ADOPT IN-HOUSE MATERIAL GENERATION |
Savings: $69,744 Cost: $194,100 |
$(-3,189) | (-56,132) | $(-511) | (-40) | - | - | - | - | $(-1,000) | - | $74,444 | - | - | - |
$(-3,189) (-56,132) kWh |
$(-511) (-40) kW-months/year |
- - MMBtu |
- - Tgal |
$(-1,000) - $ |
$74,444 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.6231 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED |
Savings: $12,237 Cost: $40,000 |
$1,509 | 29,700 | - | - | $10,728 | 1,386 | - | - | - | - | - | - | - | - |
$1,509 29,700 kWh |
- - kW-months/year |
$10,728 1,386 MMBtu |
- - Tgal |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4131 SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY |
Savings: $4,940 Cost: $4,000 |
$3,112 | 51,546 | $1,828 | 143 | - | - | - | - | - | - | - | - | - | - |
$3,112 51,546 kWh |
$1,828 143 kW-months/year |
- - MMBtu |
- - Tgal |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $4,037 Cost: $35,500 |
$2,657 | 44,928 | $1,380 | 108 | - | - | - | - | - | - | - | - | - | - |
$2,657 44,928 kWh |
$1,380 108 kW-months/year |
- - MMBtu |
- - Tgal |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 3.4114 REPLACE CITY WATER WITH RECYCLED WATER VIA COOLING TOWER |
Savings: $795 Cost: $3,230 |
- | - | - | - | - | - | $795 | 257,400 | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$795 257,400 Tgal |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 4.821 PAY BILLS ON TIME TO AVOID LATE FEES |
Savings: $576 Cost: - |
- | - | - | - | - | - | - | - | - | - | - | - | $576 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - Tgal |
- - $ |
- - $ |
$576 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.3137 USE POWER DURING OFF-PEAK PERIODS |
Savings: $567 Cost: $500 |
- | - | - | - | - | - | - | - | - | - | - | - | $567 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - Tgal |
- - $ |
- - $ |
$567 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.6218 TURN OFF EQUIPMENT WHEN NOT IN USE |
Savings: $213 Cost: - |
$124 | 2,141 | $89 | 7 | - | - | - | - | - | - | - | - | - | - |
$124 2,141 kWh |
$89 7 kW-months/year |
- - MMBtu |
- - Tgal |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $93,109 Cost: $277,330 |
$4,213 | 72,183 | $2,786 | 218 | $10,728 | 1,386 | $795 | 257,400 | $(-1,000) | - | $74,444 | - | $1,143 | - | $4,213 72,183 kWh |
$2,786 218 kW-months/year |
$10,728 1,386 MMBtu |
$795 257,400 Tgal |
$(-1,000) - $ |
$74,444 - $ |
$1,143 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $71,328 Cost: $197,330 |
$(-3,065) | (-53,991) | $(-422) | (-33) | - | - | $795 | 257,400 | $(-1,000) | - | $74,444 | - | $576 | - | $(-3,065) (-53,991) kWh |
$(-422) (-33) kW-months/year |
- - MMBtu |
$795 257,400 Tgal |
$(-1,000) - $ |
$74,444 - $ |
$576 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | Tgal | $ | $ | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Administrative Changes | Ancillary Material Cost | One-time Revenue or Avoided Cost | Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Administrative Changes | Ancillary Material Cost | One-time Revenue or Avoided Cost |