Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Maine |
---|---|
Assessment Year | 1999 |
Principal Product | Ice-cream |
NAICS | n/a |
SIC | 2024 - Ice Cream And Frozen Desserts |
Sales | $1,000,000-$5,000,000 |
# of Employees | 90 |
Plant Area (Sq.Ft.) | 12,100 |
Annual Production | 8,100,000 Pieces |
Production Hrs. Annual | 4,500 |
Location (State) | VT |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $281,160 | 5,175,850 | kWh | $0.05 |
Electricity Demand | $78,110 | 11,261 | kW-months/year | $6.94 |
Electricity Fees | $80,126 | - | $ | - |
Fuel Oil #2 | $40,546 | 7,587 | MMBtu | $5.34 |
TOTAL ENERGY COSTS | $482,867 | |||
RECOMMENDED SAVINGS* | $37,743 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $8,992 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | LPG | Fuel Oil #2 | Solid Waste (non-haz) | Primary Raw Material | Electricity Usage | Electricity Demand | LPG | Fuel Oil #2 | Solid Waste (non-haz) | Primary Raw Material | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | MMBtu | $ | lb | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.1311 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT |
Savings: $5,108 Cost: $11,800 |
$6,480 | 72,098 | $1,500 | 216 | $(-2,872) | (-307) | - | - | - | - | - | - |
$6,480 72,098 kWh |
$1,500 216 kW-months/year |
$(-2,872) (-307) MMBtu |
- - MMBtu |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.2523 REDUCE INFILTRATION TO REFRIGERATED AREAS; ISOLATE HOT EQUIPMENT FROM REFRIGERATED AREAS |
Savings: $4,700 Cost: $900 |
$4,700 | 52,169 | - | - | - | - | - | - | - | - | - | - |
$4,700 52,169 kWh |
- - kW-months/year |
- - MMBtu |
- - MMBtu |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $2,563 Cost: $2,500 |
$2,350 | 22,860 | $213 | 33 | - | - | - | - | - | - | - | - |
$2,350 22,860 kWh |
$213 33 kW-months/year |
- - MMBtu |
- - MMBtu |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $512 Cost: $185 |
$512 | 5,569 | - | - | - | - | - | - | - | - | - | - |
$512 5,569 kWh |
- - kW-months/year |
- - MMBtu |
- - MMBtu |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.1113 REDUCE COMBUSTION AIR FLOW TO OPTIMUM |
Savings: $337 Cost: $400 |
- | - | - | - | - | - | $337 | 63 | - | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$337 63 MMBtu |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $325 Cost: $400 |
- | - | - | - | - | - | $325 | 48 | - | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$325 48 MMBtu |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $319 Cost: $590 |
- | - | - | - | - | - | $319 | 9 | - | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$319 9 MMBtu |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $236 Cost: $93 |
- | - | - | - | - | - | $236 | 28 | - | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$236 28 MMBtu |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 3.7214 REDUCE OR ELIMINATE WASTE |
Savings: $23,643 Cost: $31,200 |
- | - | - | - | - | - | - | - | $2,193 | 58,500 | $21,450 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - MMBtu |
$2,193 58,500 lb |
$21,450 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $37,743 Cost: $48,068 |
$14,042 | 152,696 | $1,713 | 249 | $(-2,872) | (-307) | $1,217 | 148 | $2,193 | 58,500 | $21,450 | - | $14,042 152,696 kWh |
$1,713 249 kW-months/year |
$(-2,872) (-307) MMBtu |
$1,217 148 MMBtu |
$2,193 58,500 lb |
$21,450 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $8,992 Cost: $5,068 |
$7,562 | 80,598 | $213 | 33 | - | - | $1,217 | 148 | - | - | - | - | $7,562 80,598 kWh |
$213 33 kW-months/year |
- - MMBtu |
$1,217 148 MMBtu |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | MMBtu | $ | lb | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | LPG | Fuel Oil #2 | Solid Waste (non-haz) | Primary Raw Material | Electricity Usage | Electricity Demand | LPG | Fuel Oil #2 | Solid Waste (non-haz) | Primary Raw Material |