Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Maine |
---|---|
Assessment Year | 2000 |
Principal Product | Pine Lumber |
NAICS | n/a |
SIC | 2421 - Sawmills And Planing Mills, General |
Sales | $1,000,000-$5,000,000 |
# of Employees | 45 |
Plant Area (Sq.Ft.) | 43,070 |
Annual Production | 8,000,000 Thousand Feet |
Production Hrs. Annual | 2,350 |
Location (State) | ME |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $173,014 | 1,976,846 | kWh | $0.09 |
Electricity Demand | $6,031 | 7,758 | kW-months/year | $0.78 |
Electricity Fees | $469 | - | $ | - |
Fuel Oil #2 | $3,111 | 447 | MMBtu | $6.96 |
TOTAL ENERGY COSTS | $182,625 | |||
RECOMMENDED SAVINGS* | $121,262 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $36,632 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Fuel Oil #2 | Solid Waste (non-haz) | Increase in Production | Electricity Usage | Electricity Demand | Fuel Oil #2 | Solid Waste (non-haz) | Increase in Production | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | lb | $ | % | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $35,240 Cost: $66,900 |
$35,240 | 497,069 | - | - | - | - | - | - | - | - |
$35,240 497,069 kWh |
- - kW-months/year |
- - MMBtu |
- - lb |
- - % |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $2,062 Cost: $5,845 |
$1,542 | 19,637 | $520 | 98 | - | - | - | - | - | - |
$1,542 19,637 kWh |
$520 98 kW-months/year |
- - MMBtu |
- - lb |
- - % |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $1,392 Cost: $340 |
$1,392 | 19,637 | - | - | - | - | - | - | - | - |
$1,392 19,637 kWh |
- - kW-months/year |
- - MMBtu |
- - lb |
- - % |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.6231 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED |
Savings: $241 Cost: $450 |
$241 | 3,517 | - | - | - | - | - | - | - | - |
$241 3,517 kWh |
- - kW-months/year |
- - MMBtu |
- - lb |
- - % |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.2123 INSULATE FEEDWATER TANK |
Savings: $88 Cost: $250 |
- | - | - | - | $88 | 66 | - | - | - | - |
- - kWh |
- - kW-months/year |
$88 66 MMBtu |
- - lb |
- - % |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 3.1192 REDUCE SCRAP PRODUCTION |
Savings: $61,470 Cost: $204,600 |
- | - | - | - | - | - | $(-3,330) | 666,000 | $64,800 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$(-3,330) 666,000 lb |
$64,800 - % |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 4.114 ADD/MODIFY EQUIPMENT TO IMPROVE DRYING PROCESS |
Savings: $20,769 Cost: - |
- | - | - | - | - | - | - | - | $20,769 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - lb |
$20,769 - % |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $121,262 Cost: $278,385 |
$38,415 | 539,860 | $520 | 98 | $88 | 66 | $(-3,330) | 666,000 | $85,569 | - | $38,415 539,860 kWh |
$520 98 kW-months/year |
$88 66 MMBtu |
$(-3,330) 666,000 lb |
$85,569 - % |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $36,632 Cost: $67,240 |
$36,632 | 516,706 | - | - | - | - | - | - | - | - | $36,632 516,706 kWh |
- - kW-months/year |
- - MMBtu |
- - lb |
- - % |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | lb | $ | % | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Fuel Oil #2 | Solid Waste (non-haz) | Increase in Production | Electricity Usage | Electricity Demand | Fuel Oil #2 | Solid Waste (non-haz) | Increase in Production |