Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Maine |
---|---|
Assessment Year | 2000 |
Principal Product | Juice |
NAICS | n/a |
SIC | 2037 - Frozen Fruits And Vegetables |
Sales | $10,000,000-$50,000,000 |
# of Employees | 40 |
Plant Area (Sq.Ft.) | 38,000 |
Annual Production | 3,750 Thousand Gallons |
Production Hrs. Annual | 2,875 |
Location (State) | ME |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $105,743 | 1,421,161 | kWh | $0.07 |
Electricity Demand | $44,976 | 5,411 | kW-months/year | $8.31 |
Electricity Fees | $4,644 | - | $ | - |
LPG | $58,332 | 6,064 | MMBtu | $9.62 |
TOTAL ENERGY COSTS | $213,695 | |||
RECOMMENDED SAVINGS* | $119,928 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Electricity Fees | LPG | Fuel Oil #2 | Personnel Changes | Primary Raw Material | Water Consumption | Electricity Usage | Electricity Demand | Electricity Fees | LPG | Fuel Oil #2 | Personnel Changes | Primary Raw Material | Water Consumption | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | $ | MMBtu | $ | MMBtu | $ | $ | $ | $ | $ | Tgal | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.1333 CONVERT COMBUSTION EQUIPMENT TO BURN OIL |
Savings: $8,563 Cost: $9,360 |
- | - | - | - | - | - | $40,500 | 3,726 | $(-31,937) | (-3,726) | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
- - $ |
$40,500 3,726 MMBtu |
$(-31,937) (-3,726) MMBtu |
- - $ |
- - $ |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $7,184 Cost: $14,916 |
$4,838 | 65,064 | $2,346 | 282 | - | - | - | - | - | - | - | - | - | - | - | - |
$4,838 65,064 kWh |
$2,346 282 kW-months/year |
- - $ |
- - MMBtu |
- - MMBtu |
- - $ |
- - $ |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $4,620 Cost: $13,380 |
$2,030 | 18,757 | - | - | - | - | $2,590 | 248 | - | - | - | - | - | - | - | - |
$2,030 18,757 kWh |
- - kW-months/year |
- - $ |
$2,590 248 MMBtu |
- - MMBtu |
- - $ |
- - $ |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7492 USE PROPER THICKNESS OF INSULATION ON BUILDING ENVELOPE |
Savings: $1,337 Cost: $2,440 |
$1,337 | 50,117 | - | - | - | - | - | - | - | - | - | - | - | - | - | - |
$1,337 50,117 kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
- - MMBtu |
- - $ |
- - $ |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.8112 COMBINE UTILITY METERS |
Savings: $1,333 Cost: $3,910 |
- | - | - | - | $1,333 | - | - | - | - | - | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$1,333 - $ |
- - MMBtu |
- - MMBtu |
- - $ |
- - $ |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.2136 INSTALL / REPAIR INSULATION ON STEAM LINES |
Savings: $820 Cost: $1,637 |
- | - | - | - | - | - | $820 | 68 | - | - | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
- - $ |
$820 68 MMBtu |
- - MMBtu |
- - $ |
- - $ |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.8123 PAY UTILITY BILLS ON TIME |
Savings: $484 Cost: - |
- | - | - | - | $484 | - | - | - | - | - | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$484 - $ |
- - MMBtu |
- - MMBtu |
- - $ |
- - $ |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.2123 INSULATE FEEDWATER TANK |
Savings: $412 Cost: $80 |
- | - | - | - | - | - | $412 | 34 | - | - | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
- - $ |
$412 34 MMBtu |
- - MMBtu |
- - $ |
- - $ |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 3.7212 IMPROVED MATERIAL HANDLING (MIXING AND TRANSFER) |
Savings: $87,478 Cost: $8,500 |
- | - | - | - | - | - | - | - | - | - | - | - | $87,478 | - | - | - |
- - kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
- - MMBtu |
- - $ |
$87,478 - $ |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 3.4156 USE FLOW CONTROL VALVES ON EQUIPMENT TO OPTIMIZE WATER USE |
Savings: $197 Cost: $240 |
- | - | - | - | - | - | - | - | - | - | - | - | - | - | $197 | - |
- - kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
- - MMBtu |
- - $ |
- - $ |
$197 - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
11: 4.512 CONDENSE OPERATION INTO ONE BUILDING |
Savings: $7,500 Cost: $6,043 |
- | - | - | - | - | - | - | - | - | - | $7,500 | - | - | - | - | - |
- - kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
- - MMBtu |
$7,500 - $ |
- - $ |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $119,928 Cost: $60,506 |
$8,205 | 133,938 | $2,346 | 282 | $1,817 | - | $44,322 | 4,076 | $(-31,937) | (-3,726) | $7,500 | - | $87,478 | - | $197 | - | $8,205 133,938 kWh |
$2,346 282 kW-months/year |
$1,817 - $ |
$44,322 4,076 MMBtu |
$(-31,937) (-3,726) MMBtu |
$7,500 - $ |
$87,478 - $ |
$197 - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
- - MMBtu |
- - $ |
- - $ |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | $ | MMBtu | $ | MMBtu | $ | $ | $ | $ | $ | Tgal | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Electricity Fees | LPG | Fuel Oil #2 | Personnel Changes | Primary Raw Material | Water Consumption | Electricity Usage | Electricity Demand | Electricity Fees | LPG | Fuel Oil #2 | Personnel Changes | Primary Raw Material | Water Consumption |