IAC Assessment: MO0270
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: MO0270
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Missouri, Rolla
Assessment Year 1999
Principal Product Optical Lenses and Fused Multifocals
NAICS n/a
SIC 3851 - Ophthalmic Goods
Sales $10,000,000-$50,000,000
# of Employees 150
Plant Area (Sq.Ft.) 40,000
Annual Production 850,000 Pieces
Production Hrs. Annual 2,080
Location (State) MO
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $293,641 5,643,611 kWh $0.05
Electricity Demand $34,716 1,406 kW-months/year $24.69
Electricity Fees $43,625 - $ -
TOTAL ENERGY COSTS $413,260
RECOMMENDED SAVINGS* $97,739 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $10,783
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Solid Waste (non-haz) Ancillary Material Cost Electricity Usage Electricity Demand Solid Waste (non-haz) Ancillary Material Cost
$ kWh $ kW-months/year $ lb $ $
01: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS Savings:
$10,783
Cost:
$36,941
$9,005 150,645 $1,778 72 - - - - $9,005
150,645
kWh
$1,778
72
kW-months/year
-
-
lb
-
-
$
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$4,802
Cost:
$10,421
$4,012 67,116 $790 32 - - - - $4,012
67,116
kWh
$790
32
kW-months/year
-
-
lb
-
-
$
03: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT Savings:
$235
Cost:
$53
$210 3,517 $25 1 - - - - $210
3,517
kWh
$25
1
kW-months/year
-
-
lb
-
-
$
04: 3.1175 USE A DIFFERENT OR RECYCLED RAW MATERIAL Savings:
$720
Cost:
$1,800
- - - - $720 120 - - -
-
kWh
-
-
kW-months/year
$720
120
lb
-
-
$
05: 2.3131 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS Savings:
$76,792
Cost:
-
- - - - - - $76,792 - -
-
kWh
-
-
kW-months/year
-
-
lb
$76,792
-
$
06: 2.3133 CONSIDER THREE OR FOUR DAYS AROUND-THE-CLOCK OPERATION RATHER THAN ONE OR TWO SHIFTS PER DAY Savings:
$4,407
Cost:
-
- - - - - - $4,407 - -
-
kWh
-
-
kW-months/year
-
-
lb
$4,407
-
$
TOTAL RECOMMENDED Savings:
$97,739
Cost:
$49,215
$13,227 221,278 $2,593 105 $720 120 $81,199 - $13,227
221,278
kWh
$2,593
105
kW-months/year
$720
120
lb
$81,199
-
$
TOTAL IMPLEMENTED Savings:
$10,783
Cost:
$36,941
$9,005 150,645 $1,778 72 - - - - $9,005
150,645
kWh
$1,778
72
kW-months/year
-
-
lb
-
-
$
Savings
Cost
$ kWh $ kW-months/year $ lb $ $
Electricity Usage Electricity Demand Solid Waste (non-haz) Ancillary Material Cost Electricity Usage Electricity Demand Solid Waste (non-haz) Ancillary Material Cost