Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Missouri, Rolla |
---|---|
Assessment Year | 2000 |
Principal Product | Pharmaceutical Tool and Die |
NAICS | n/a |
SIC | 3544 - Special Dies, Tools, Jigs & Fixtures |
Sales | $10,000,000-$50,000,000 |
# of Employees | 125 |
Plant Area (Sq.Ft.) | 105,000 |
Annual Production | 780,000 Pieces |
Production Hrs. Annual | 4,160 |
Location (State) | MO |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $186,124 | 3,747,069 | kWh | $0.05 |
Electricity Demand | $20,439 | 864 | kW-months/year | $23.66 |
Electricity Fees | $14,743 | - | $ | - |
Natural Gas | $11,164 | 2,571 | MMBtu | $4.34 |
TOTAL ENERGY COSTS | $249,762 | |||
RECOMMENDED SAVINGS* | $88,092 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $9,744 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Solid Waste (non-haz) | Personnel Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Solid Waste (non-haz) | Personnel Changes | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | lb | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $3,098 Cost: $3,399 |
$2,800 | 52,169 | $298 | 13 | - | - | - | - | - | - |
$2,800 52,169 kWh |
$298 13 kW-months/year |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $7,238 Cost: $9,332 |
$6,545 | 122,216 | $693 | 29 | - | - | - | - | - | - |
$6,545 122,216 kWh |
$693 29 kW-months/year |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $2,506 Cost: $175 |
$2,265 | 42,204 | $241 | 10 | - | - | - | - | - | - |
$2,265 42,204 kWh |
$241 10 kW-months/year |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $1,270 Cost: $825 |
$617 | 11,430 | $653 | 28 | - | - | - | - | - | - |
$617 11,430 kWh |
$653 28 kW-months/year |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 3.7198 REDUCE / ELIMINATE USE OF DISPOSABLE PRODUCT |
Savings: $11,232 Cost: $2,160 |
- | - | - | - | $11,232 | 1,872 | - | - | - | - |
- - kWh |
- - kW-months/year |
$11,232 1,872 lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 3.5315 LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER |
Savings: $2,496 Cost: - |
- | - | - | - | $2,496 | 24 | - | - | - | - |
- - kWh |
- - kW-months/year |
$2,496 24 lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 4.445 INSTALL EQUIPMENT TO MOVE PRODUCT |
Savings: $58,989 Cost: $7,500 |
- | - | - | - | - | - | $58,989 | - | - | - |
- - kWh |
- - kW-months/year |
- - lb |
$58,989 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.3131 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS |
Savings: $1,263 Cost: - |
- | - | - | - | - | - | - | - | $1,263 | - |
- - kWh |
- - kW-months/year |
- - lb |
- - $ |
$1,263 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $88,092 Cost: $23,391 |
$12,227 | 228,019 | $1,885 | 80 | $13,728 | 1,896 | $58,989 | - | $1,263 | - | $12,227 228,019 kWh |
$1,885 80 kW-months/year |
$13,728 1,896 lb |
$58,989 - $ |
$1,263 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $9,744 Cost: $9,507 |
$8,810 | 164,420 | $934 | 39 | - | - | - | - | - | - | $8,810 164,420 kWh |
$934 39 kW-months/year |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | lb | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Solid Waste (non-haz) | Personnel Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Solid Waste (non-haz) | Personnel Changes | Ancillary Material Cost |