Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | North Carolina State |
---|---|
Assessment Year | 1996 |
Principal Product | Pickled Cucumbers |
NAICS | n/a |
SIC | 2035 - Pickles, Sauces, And Salad Dressings |
Sales | $50,000,000-$100,000,000 |
# of Employees | 250 |
Plant Area (Sq.Ft.) | 200,000 |
Annual Production | 7,500,000 Units |
Production Hrs. Annual | 5,000 |
Location (State) | NC |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $261,443 | 7,924,678 | kWh | $0.03 |
Electricity Demand | $141,690 | 16,761 | kW-months/year | $8.45 |
Fuel Oil #6 | $179,894 | 56,414 | MMBtu | $3.19 |
TOTAL ENERGY COSTS | $1,124,527 | |||
RECOMMENDED SAVINGS* | $70,201 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $8,289 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Fuel Oil #6 | Water Disposal | Ancillary Material Cost | Electricity Usage | Electricity Demand | Fuel Oil #6 | Water Disposal | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | Tgal | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $1,850 Cost: $1,578 |
$1,091 | 33,118 | $759 | 91 | - | - | - | - | - | - |
$1,091 33,118 kWh |
$759 91 kW-months/year |
- - MMBtu |
- - Tgal |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $108 Cost: $560 |
$50 | 1,465 | $18 | 2 | - | - | - | - | $40 | - |
$50 1,465 kWh |
$18 2 kW-months/year |
- - MMBtu |
- - Tgal |
$40 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7134 USE PHOTOCELL CONTROLS |
Savings: $2,242 Cost: $660 |
$1,014 | 30,774 | $1,228 | 148 | - | - | - | - | - | - |
$1,014 30,774 kWh |
$1,228 148 kW-months/year |
- - MMBtu |
- - Tgal |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $859 Cost: $30 |
$535 | 16,120 | $324 | 39 | - | - | - | - | - | - |
$535 16,120 kWh |
$324 39 kW-months/year |
- - MMBtu |
- - Tgal |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7447 INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS |
Savings: $605 Cost: $600 |
$162 | 4,982 | $443 | 50 | - | - | - | - | - | - |
$162 4,982 kWh |
$443 50 kW-months/year |
- - MMBtu |
- - Tgal |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $2,187 Cost: $3,224 |
$1,640 | 49,824 | $547 | 66 | - | - | - | - | - | - |
$1,640 49,824 kWh |
$547 66 kW-months/year |
- - MMBtu |
- - Tgal |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.1233 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO |
Savings: $1,902 Cost: $600 |
- | - | - | - | $1,902 | 598 | - | - | - | - |
- - kWh |
- - kW-months/year |
$1,902 598 MMBtu |
- - Tgal |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 3.4111 USE CLOSED CYCLE PROCESS TO MINIMIZE WASTE WATER PRODUCTION |
Savings: $1,683 Cost: $2,500 |
$(-205) | (-6,155) | $(-250) | (-30) | - | - | $2,138 | 450,000 | - | - |
$(-205) (-6,155) kWh |
$(-250) (-30) kW-months/year |
- - MMBtu |
$2,138 450,000 Tgal |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 3.4114 REPLACE CITY WATER WITH RECYCLED WATER VIA COOLING TOWER |
Savings: $58,765 Cost: $10,360 |
$(-1,034) | (-31,360) | $(-393) | (-43) | - | - | $60,192 | 12,672,000 | - | - |
$(-1,034) (-31,360) kWh |
$(-393) (-43) kW-months/year |
- - MMBtu |
$60,192 12,672,000 Tgal |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $70,201 Cost: $20,112 |
$3,253 | 98,768 | $2,676 | 323 | $1,902 | 598 | $62,330 | 13,122,000 | $40 | - | $3,253 98,768 kWh |
$2,676 323 kW-months/year |
$1,902 598 MMBtu |
$62,330 13,122,000 Tgal |
$40 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $8,289 Cost: $6,622 |
$3,795 | 115,181 | $2,552 | 307 | $1,902 | 598 | - | - | $40 | - | $3,795 115,181 kWh |
$2,552 307 kW-months/year |
$1,902 598 MMBtu |
- - Tgal |
$40 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | Tgal | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Fuel Oil #6 | Water Disposal | Ancillary Material Cost | Electricity Usage | Electricity Demand | Fuel Oil #6 | Water Disposal | Ancillary Material Cost |