Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | North Carolina State |
---|---|
Assessment Year | 1999 |
Principal Product | Fiber batting for furniture |
NAICS | n/a |
SIC | 2290 - |
Sales | $10,000,000-$50,000,000 |
# of Employees | 82 |
Plant Area (Sq.Ft.) | 200,000 |
Annual Production | 15,000,000 Pounds |
Production Hrs. Annual | 6,000 |
Location (State) | NC |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $65,800 | 2,231,243 | kWh | $0.03 |
Electricity Demand | $59,403 | 6,306 | kW-months/year | $9.42 |
Electricity Fees | $720 | - | $ | - |
Natural Gas | $62,190 | 12,274 | MMBtu | $5.07 |
TOTAL ENERGY COSTS | $188,473 | |||
RECOMMENDED SAVINGS* | $143,859 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $45,360 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Solid Waste (non-haz) | Personnel Changes | Administrative Changes | Primary Raw Material | Ancillary Material Cost | By-product Production | Increase in Production | Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Solid Waste (non-haz) | Personnel Changes | Administrative Changes | Primary Raw Material | Ancillary Material Cost | By-product Production | Increase in Production | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | Tgal | $ | lb | $ | $ | $ | $ | $ | $ | $ | $ | $ | $ | $ | % | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $384 Cost: $120 |
$256 | 8,206 | $128 | 14 | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - |
$256 8,206 kWh |
$128 14 kW-months/year |
- - MMBtu |
- - Tgal |
- - lb |
- - $ |
- - $ |
- - $ |
- - $ |
- - $ |
- - % |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $235 Cost: $250 |
$235 | 7,913 | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - |
$235 7,913 kWh |
- - kW-months/year |
- - MMBtu |
- - Tgal |
- - lb |
- - $ |
- - $ |
- - $ |
- - $ |
- - $ |
- - % |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $3,937 Cost: $1,000 |
- | - | - | - | $3,937 | 776 | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$3,937 776 MMBtu |
- - Tgal |
- - lb |
- - $ |
- - $ |
- - $ |
- - $ |
- - $ |
- - % |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $972 Cost: $907 |
$496 | 16,706 | $476 | 51 | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - |
$496 16,706 kWh |
$476 51 kW-months/year |
- - MMBtu |
- - Tgal |
- - lb |
- - $ |
- - $ |
- - $ |
- - $ |
- - $ |
- - % |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4226 USE / PURCHASE OPTIMUM SIZED COMPRESSOR |
Savings: $12,762 Cost: - |
$7,788 | 264,068 | $4,974 | 528 | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - |
$7,788 264,068 kWh |
$4,974 528 kW-months/year |
- - MMBtu |
- - Tgal |
- - lb |
- - $ |
- - $ |
- - $ |
- - $ |
- - $ |
- - % |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7491 INSULATE GLAZING, WALLS, CEILINGS, AND ROOFS |
Savings: $5,335 Cost: $20,780 |
- | - | - | - | $5,335 | 1,052 | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$5,335 1,052 MMBtu |
- - Tgal |
- - lb |
- - $ |
- - $ |
- - $ |
- - $ |
- - $ |
- - % |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7313 RECYCLE AIR FOR HEATING, VENTILATION AND AIR CONDITIONING |
Savings: $5,794 Cost: $2,500 |
- | - | - | - | $5,794 | 1,134 | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$5,794 1,134 MMBtu |
- - Tgal |
- - lb |
- - $ |
- - $ |
- - $ |
- - $ |
- - $ |
- - % |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 3.1192 REDUCE SCRAP PRODUCTION |
Savings: $2,360 Cost: $4,100 |
- | - | - | - | - | - | - | - | $120 | 4 | - | - | - | - | $2,240 | - | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - Tgal |
$120 4 lb |
- - $ |
- - $ |
$2,240 - $ |
- - $ |
- - $ |
- - % |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 4.521 CLEAR AND RENT EXISTING SPACE |
Savings: $26,000 Cost: $640 |
- | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | $26,000 | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - Tgal |
- - lb |
- - $ |
- - $ |
- - $ |
- - $ |
$26,000 - $ |
- - % |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 4.423 MOVE PRODUCT USING MECHANICAL MEANS |
Savings: $3,600 Cost: $500 |
- | - | - | - | - | - | - | - | - | - | $3,600 | - | - | - | - | - | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - Tgal |
- - lb |
$3,600 - $ |
- - $ |
- - $ |
- - $ |
- - $ |
- - % |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
11: 4.611 BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE |
Savings: $680 Cost: $1,000 |
- | - | - | - | - | - | - | - | - | - | $(-500) | - | $1,430 | - | - | - | $(-250) | - | - | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - Tgal |
- - lb |
$(-500) - $ |
$1,430 - $ |
- - $ |
$(-250) - $ |
- - $ |
- - % |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
12: 4.424 IMPROVE SPACE COMFORT CONDITIONING |
Savings: $81,800 Cost: $13,500 |
- | - | - | - | - | - | $(-100) | (-20,000) | - | - | - | - | - | - | - | - | - | - | - | - | $81,900 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$(-100) (-20,000) Tgal |
- - lb |
- - $ |
- - $ |
- - $ |
- - $ |
- - $ |
$81,900 - % |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $143,859 Cost: $45,297 |
$8,775 | 296,893 | $5,578 | 593 | $15,066 | 2,962 | $(-100) | (-20,000) | $120 | 4 | $3,100 | - | $1,430 | - | $2,240 | - | $(-250) | - | $26,000 | - | $81,900 | - | $8,775 296,893 kWh |
$5,578 593 kW-months/year |
$15,066 2,962 MMBtu |
$(-100) (-20,000) Tgal |
$120 4 lb |
$3,100 - $ |
$1,430 - $ |
$2,240 - $ |
$(-250) - $ |
$26,000 - $ |
$81,900 - % |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $45,360 Cost: $30,797 |
$987 | 32,825 | $604 | 65 | $11,129 | 2,186 | - | - | $120 | 4 | $3,100 | - | $1,430 | - | $2,240 | - | $(-250) | - | $26,000 | - | - | - | $987 32,825 kWh |
$604 65 kW-months/year |
$11,129 2,186 MMBtu |
- - Tgal |
$120 4 lb |
$3,100 - $ |
$1,430 - $ |
$2,240 - $ |
$(-250) - $ |
$26,000 - $ |
- - % |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | Tgal | $ | lb | $ | $ | $ | $ | $ | $ | $ | $ | $ | $ | $ | % | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Solid Waste (non-haz) | Personnel Changes | Administrative Changes | Primary Raw Material | Ancillary Material Cost | By-product Production | Increase in Production | Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Solid Waste (non-haz) | Personnel Changes | Administrative Changes | Primary Raw Material | Ancillary Material Cost | By-product Production | Increase in Production |