Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | North Carolina State |
---|---|
Assessment Year | 2000 |
Principal Product | Metal ties |
NAICS | n/a |
SIC | 3429 - Hardware, Nec |
Sales | $10,000,000-$50,000,000 |
# of Employees | 180 |
Plant Area (Sq.Ft.) | 113,060 |
Annual Production | 2,147,483,647 Pieces |
Production Hrs. Annual | 4,000 |
Location (State) | NC |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $335,816 | 7,388,922 | kWh | $0.05 |
Electricity Demand | $105,581 | 19,105 | kW-months/year | $5.53 |
Electricity Fees | $17,094 | - | $ | - |
LPG | $68,143 | 9,110 | MMBtu | $7.48 |
TOTAL ENERGY COSTS | $526,709 | |||
RECOMMENDED SAVINGS* | $51,000 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | LPG | Solid Waste (non-haz) | Increase in Production | Electricity Usage | Electricity Demand | LPG | Solid Waste (non-haz) | Increase in Production | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | lb | $ | % | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $2,836 Cost: $1,000 |
$2,079 | 45,721 | $757 | 137 | - | - | - | - | - | - |
$2,079 45,721 kWh |
$757 137 kW-months/year |
- - MMBtu |
- - lb |
- - % |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4224 UPGRADE CONTROLS ON COMPRESSORS |
Savings: $10,033 Cost: $5,000 |
$10,033 | 220,692 | - | - | - | - | - | - | - | - |
$10,033 220,692 kWh |
- - kW-months/year |
- - MMBtu |
- - lb |
- - % |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4235 REMOVE OR CLOSE OFF UNNEEDED COMPRESSED AIR LINES |
Savings: $975 Cost: $2,640 |
$784 | 17,292 | $191 | 34 | - | - | - | - | - | - |
$784 17,292 kWh |
$191 34 kW-months/year |
- - MMBtu |
- - lb |
- - % |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.5196 USE SMALL NUMBER OF HIGH OUTPUT UNITS INSTEAD OF MANY SMALL INEFFICIENT UNITS |
Savings: $7,128 Cost: $20,000 |
$5,223 | 114,889 | $1,905 | 344 | - | - | - | - | - | - |
$5,223 114,889 kWh |
$1,905 344 kW-months/year |
- - MMBtu |
- - lb |
- - % |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $689 Cost: $1,428 |
$399 | 8,499 | $290 | 52 | - | - | - | - | - | - |
$399 8,499 kWh |
$290 52 kW-months/year |
- - MMBtu |
- - lb |
- - % |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7241 INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT |
Savings: $17,072 Cost: $24,000 |
$17,072 | 375,440 | - | - | - | - | - | - | - | - |
$17,072 375,440 kWh |
- - kW-months/year |
- - MMBtu |
- - lb |
- - % |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.2424 USE HEAT IN FLUE GASES TO PREHEAT PRODUCTS OR MATERIALS |
Savings: $3,506 Cost: $5,416 |
- | - | - | - | $3,506 | 469 | - | - | - | - |
- - kWh |
- - kW-months/year |
$3,506 469 MMBtu |
- - lb |
- - % |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 3.5313 INCREASE AMOUNT OF WASTE RECOVERED FOR RESALE |
Savings: $75 Cost: $260 |
- | - | - | - | - | - | $75 | 5,000 | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$75 5,000 lb |
- - % |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.1321 REPLACE FOSSIL FUEL EQUIPMENT WITH ELECTRICAL EQUIPMENT |
Savings: $8,686 Cost: $25,740 |
$(-13,728) | (-301,876) | $(-4,436) | (-802) | $18,850 | 2,520 | - | - | $8,000 | - |
$(-13,728) (-301,876) kWh |
$(-4,436) (-802) kW-months/year |
$18,850 2,520 MMBtu |
- - lb |
$8,000 - % |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $51,000 Cost: $85,484 |
$21,862 | 480,657 | $(-1,293) | (-235) | $22,356 | 2,989 | $75 | 5,000 | $8,000 | - | $21,862 480,657 kWh |
$(-1,293) (-235) kW-months/year |
$22,356 2,989 MMBtu |
$75 5,000 lb |
$8,000 - % |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - MMBtu |
- - lb |
- - % |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | lb | $ | % | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | LPG | Solid Waste (non-haz) | Increase in Production | Electricity Usage | Electricity Demand | LPG | Solid Waste (non-haz) | Increase in Production |